Road building
Turns out: the condition of the Flórián Square South Bridge is worse than expected
The renovation of the southern bridge at Flórián Square is currently underway. As we have reported in detail several times in our newspaper rel="noopener">reported in detail in our newspaper, is being carried out by KM Építő Kft.. The investor Budapesti Közlekedési Központ (BKK) is now reporting that during the scheduled demolition and milling work – when the track surface and loose insulation were removed – previously unknown defects in the reinforced concrete track slab and the concrete crust became visible.
Planners and engineers working on the restoration have been sampling and taking instrumental measurements to assess the extent and extent of the damage, paying particular attention to possible salt contamination, they say. They add that the results of the independent investigation have now been received: the expert has revealed significant damage to the south bridge deck that was not visible before the renovation work started and only became apparent after the demolition work was completed.
The safest solutions are chosen
The worse-than-expected technical condition of the flyover is an obstacle to the proper design of the new insulation. Therefore, repairs beyond the scope of the current contract have become necessary, which affect the cost and timing of the works and without which the subgrade would be further damaged.
The experts have chosen the safest and most appropriate technical solution to ensure that the southern flyover can be used safely for decades to come.
KM Építő has started to repair the cantilevered parts of the deck, as they are essential for the stable and operational use of the bridge.
KM Építő solves unprecedented challenges
The problems identified will require significant additional work, so the partial technical handover of the southern bridge is scheduled for November.
The overpass will be reconstructed with more technical content than originally planned, including the repair of the trackbed. This will take longer than planned due to unforeseen defects. This means that the next phase of the renovation can only start afterwards, when the traffic on the renewed southern bridge will be back to the normal traffic flow from Szentendrei út towards Pest and the northern bridge will be closed.
As with the south bridge, the renovation of the north bridge will begin with demolition and a thorough inspection of the deck, and it is assumed that the contractor will encounter a similar situation after demolition as the south bridge, which is currently under renovation.
Overhaul of over 40-year-old flyovers has become unavoidable
The Flórián Square flyovers were last renovated in 2002-2003. Their modernisation is necessary to ensure that the section of road, which plays a major role in the transport of the capital and the agglomeration, can be used safely for decades to come.
The South Bridge was closed on 1 March; due to the necessary traffic restrictions, BKK is asking users to use public transport during the renovation, if possible, to reduce traffic congestion in the area. At the same time, motorists are advised to avoid Flórián Square and to take an alternative route to their destination.
Source: Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
