The biggest ever domestic sporting event gets underway thanks to one of the biggest construction projects in decades

Published

Step-by-step, we present the milestones of the National Athletics Centre, built at a very tight pace but to world-class standards, in the general construction of ZÁÉV Zrt. and Magyar Építő Zrt..

The 2023 World Athletics Championships will kick off with the men's 20 km walk final at the National Athletics Centre in Budapest on 19 August. On the opening day, 11 events will take place in the morning before the official opening ceremony on Saturday evening. The event, which will run until next Sunday, will bring together 2,000 athletes from more than 200 countries in 49 events.

It took just 28 months to reach implementation

The facility, which will host the largest sporting event in Hungary to date, was built by a consortium consisting of ZÁÉV Zrt. and Magyar Építő Zrt.. Work on the arena, which will seat 40,000 people during the world championships and 15,000 people afterwards, began in November 2020, with the first major event the demolition of the nearly 60-metre-high Vituki tower block in South Pest. After that, work could begin on the monolithic structure, which was completed in June 2021. In December of the same year, the installation of the pre-assembled steel roof structure elements was completed: 48 diamond-shaped elements, each weighing nearly 100 tonnes and measuring 28 metres in height, were lifted into place.

In a similarly spectacular new phase of work, the roof will be covered with nearly 27,000 square metres of membrane by September 2022, and then 28 October 2022, the building reached its highest point. In conjunction with the topping-out ceremony, the 168-metre-long Robinson Bridge, built as a pedestrian bridge, was inaugurated, providing access between the training grounds and the stadium on Csepel Island.

Thanks to the fast pace, four months later, on 1 March, the general contractor consortium was able to commence the technical handover of the project. In May, a sound and lighting demonstration was also held at the National Athletics Centre; then, on 17 June, as part of a family festival, the facility, which will serve as a sports centre after the World Championships, was handed over, with 15,000 people took part in the opening programmes.

Extraordinary pace of work and tight schedule led to success

One of the most significant construction projects in recent decades was the Építési és Közlekedési Minisztérium project, with ZÁÉV Zrt. and Magyar Építő Zrt. carrying out the general construction. The project was executed by the consortium of Főber Zrt. and Óbuda-Újlak Zrt., with NAPUR Architect Kft. as the general contractor and NAPUR Architect Kft. as the technical contractor. The design, fabrication and erection of the central structure of the building and the erection of the steel cable support structure were carried out by KÉSZ Metaltech Kft. and KÉSZ Ipari Gyártó Kft. as part of KÉSZ Csoport. The steel and cable-roof structure was designed, manufactured and installed by the group's strategic partner bim.GROUP. The Robinson Bridge, which was built next to the NAK, was built by Hídépítő Zrt. as a subcontractor of the consortium, based on the designs of Speciálterv Kft.. WHB Elektro Kft., Zala Elektro Kft., CLH Hűtés- és Klímatechnikai Kft., Kanizsai Magasépítéstő Kft., Graboplan Kft., Épszerk-Pannónia Invest Építőipari Kft., Bayer Construct Zrt., Gedi Építő Kft. and PBM Mélyépítő Kft. were the main subcontractors.

As previously mentioned, the extraordinary pace of work and tight weekly/daily schedule, during which 400-500 people worked on the construction site every day, depending on the technological process, contributed significantly to the success of the investment. The key players in the project provided our newspaper with more details about the unparalleled construction: the interesting features of the world-class arena can be found at triple and a pair interview.