After 86 years, the tower of one of the earliest Baroque churches in Hungary has been restored

Published

The church of St Ignatius of Loyola in Győr has a modern roof thanks to the work of WHB.

The complex reconstruction of the Győr Benedictine monastery and the roof of the church of St Ignatius, which is built on it, reached its highest point with the inclusion of the period Hussars' tower. The project, which is being carried out by WEST HUNGÁRIA BAU Kft., held its bokreta celebration on 19 July.

The roof of the building complex in the heart of the city has become unsafe in several places

At the beginning of the event, which preserves the traditions of the building industry, Kelemen Sárai-Szabó blessed the completed Hussar tower and the bush on the roof of the St. Ignatius Church. The ceremony was also attended by Róbert Balázs Simon, Member of Parliament, who recalled that the school of the Benedictine orders has been operating in Győr for almost 400 years. He added that the renovation of the local centre of the Benedictines, which consists of three buildings, started eight years ago. "With the support of the Hungarian government, first the Czuczor Gergely Benedictine High School was renewed and extended with the Lloyd Palace building, and then the reconstruction of the Benedictine St Ignatius Church and the Benedictine monastery was started," the politician pointed out.

According to the information handed out at the event, the investment was necessary because the roof of the building complex in the heart of the city had become unsafe in several places; it was also necessary due to the continuous increase in the number of students at the high school; and it will also provide a worthy place for the institution's centuries-old historical collection.

Reconstruction of the lost tower based on period photographs

With the help of the contractor, our newspaper has also obtained detailed information about the development, which has now reached its highest point. As we have learned, during the renovation, which began in December, the contractor is carrying out a complete reconstruction of the complex of buildings, which consists of a convent, a church and a high school. This is scheduled to be completed by the first quarter of 2025.

According to Norbert Geszler, WHB Area Director, one of the most important parts of the renovation was the complete demolition and reconstruction of the roof of St Ignatius Church and the design and construction of a brand new Hussars Tower.

The latter was removed in 1938, and has now been reconstructed on the basis of contemporary photographs and the original wrought iron cross. The reconstructed tower is faithful to its predecessor in almost every aspect: the roof girder is made of 25 x 25 cm dried oak, while the exterior is of steel construction with a wooden reception area and a decorative tin roof.

The new towers are already in place

"We placed two small bells in the tower," added Norbert Geszler. "The 170 kg e2 bell dedicated to St Maurus and the 100 kg g2 bell dedicated to St Placidus were permanently installed on 16 July 2024, the Feast of the Assumption of Our Lady of Mount Carmel."

In addition to the liturgical space, the development will also open up previously unseen parts of the building - the tower, the attic and the treasury room.

Particular care was needed when replacing the roof

The Regional Director also addressed the most critical part of the works. They had to be exceptionally careful in replacing the roof over the priceless frescoed vault and the unique altar, while the church was still regularly welcoming worshippers. Their safety was ensured by WHB by installing a protective net under the fresco.

As another aid, a canopy was also put over the building. "This way, we are not exposed to the weather and the floors below us don't get wet," according to a report on the contractor's website.

"In the coming months, we will continue the roof replacement in the south and west wings of the Benedictine monastery," said Norbert Geszler. "We will also start the construction of the planned misting shaft in the farmyard."

The special spiral staircase nears completion

WHB shared more information about the project on its social networking site, where it says that the technical works (cold and hot cladding, surface finishes, fine finishing) are already underway in the future museum spaces of the church, following the installation of the building services and electrical installations.

"We have also begun work on new stairs and renovation of existing stairs in the church towers to access the museum space," they say. "In the west tower, the construction of a special spiral staircase is being completed, which will be free-standing without lateral mooring, and will be structurally rigid with a curved balustrade connecting the steps.

The post also revealed that the next phase of the works will include the complete demolition of the south wing of the Benedictine monastery and the construction of the reinforced concrete slab. "Here, the construction of the deck is currently being completed and the scaffolding for the installation of the canopy of the west wing, which will be part of the next phase, is being built," the post explained.

Source : Link