Railways and bridges - A game-changing digitalisation project can bring development into the 21st century

Published

Photos: STRABAG
The development of STRABAG Vasútépítő Kft., a consortium of Széchenyi István University and V-Híd, could bring a new era in railway and bridge construction in Hungary, which could make railway and bridge construction more efficient and transparent through digitalisation and automation instead of paper documentation.

The National Research, Development and Innovation Office announced a call for proposals entitled "Support for market-driven research, development and innovation projects". In 2021, the following project was successfully submitted under the leadership of STRABAG Vasútépítő Kft. led by Széchenyi University and the consortium of V-Híd Kft. with its project entitled"Integration opportunities for automation and digitalisation in railway construction, development of complex procedures to increase transparency" project.

In the latter, the objective was set to improve the digitalisation of the construction of line installations, which will enable:

  • the creation of a virtual data model to monitor the construction process, and
  • visualisation of,
  • automated tracking of the progress of construction,
  • classification and analysis in the BIM framework.

Goal: Transparency, increased impact, quality improvement

Project stakeholders expect the development to improve the quality and efficiency of implementation and overall transparency and cost-effectiveness.
The consortium reported on the progress of the project implementation so far.
The development was divided into four main parts: digitisation of the data collection process,
construction of the virtual model, visualisation of the virtual model and management of the construction processes, and digitisation of the accounts and quality assurance.

The first milestone: measuring, collecting data with millimetre-accurate imaging

The first milestone of the implementation was the testing of technologies for the survey of railway infrastructure and structures. In addition to traditional measurement methods, the applicability of ground laser scanning, LIDAR technology and photogrammetry (the latter imaging a 3-dimensional world in 3D using images of a site or object) was reviewed.

During the project, laser scanner and drone surveys were carried out on a railway track section and a bridge, and the data were processed using Autodesk Recap and CloudCompare software.
The experts also examined the advantages, disadvantages and limitations of the methods used.

The accuracy and efficiency of data collection using different tools were compared.

On the basis of this experience, proposals for digital surveys of linear installations and structures have been developed. The compatibility of 3D point clouds with BIM modelling was investigated and the necessary hardware and software requirements were determined.

Models from point clouds

The second milestone in the project was the development of the methodology for the BIM modelling of railway installations and structures. In addition to the analysis of the construction standards for BIM (Building Information Modeling), the modelling techniques were adapted to the specificities of the linear infrastructure.
In the first phase, BIM models were created using 3D point clouds generated during the survey of a railway track section and a bridge.
During this phase of the work, BIM standards and infrastructure specific applications were explored. The modelling requirements and level of detail for line facilities were defined.

The potential uses of the BIM models in construction, budgeting and operation were investigated.

Then the data structure for the schedule (BIM 4D) and the budget (5D) were developed.

Virtual and augmented reality for the construction industry

The next major phase of the project focused on the specification of the virtual models and the development of the data platform. This included a review of the visualisation and data management capabilities of the models, which was a key focus:

  • comparison of the planned and actual state,
  • monitoring of the implementation,
  • optimising material handling and other logistics tasks

A digital data platform has also been specified to support the construction process and increase efficiency.
The main achievements of the third milestone were the identification of the potential applications of virtual and augmented reality.

Power in unity - working systems can be interconnected

In addition, the potential of the BIM and GIS (Geographic Information System) systems to work together in railway and engineering construction was reviewed. The latter computer system is used to collect, store, manage and analyse data related to geographic location. GIS is also suitable for information visualisation, observation and modelling of geographic phenomena.
Also in this development phase, the development concept for the digital quality assurance platform was
prepared, which automates the method of storing and updating documentation. In order to speed up the control processes, the paper-based handover will be digitally supported.

Transparency, reduced administrative and environmental burden

The fourth milestone of the project involves the development of the data platform.
During the development of railway infrastructure and the construction of the
works, a significant amount of quality assurance documentation is produced, up to 5-6 thousand pages for each project, which must be submitted in several copies to the client.

The aim of the development was to create a modern, efficient digital platform that significantly increases transparency, reduces paper use and administrative burden. It will also speed up decision-making and support the quality assurance processes for engineering and railway projects.

Supportive background for decision-making

The new system is a digital map and database platform for real-time data capture and management, accurately documenting site inspections and test results.
Through geo-spatial integration, the system records sampling points and inspection results on a map and displays the data in structured tables.

The digital workflow makes quality assurance tasks transparent.

Decision-making processes are supported by the system's automatic evaluation and reporting functionality. Users can filter and analyse data according to a number of criteria, such as time, number of sections, layers, project phase, etc. The platform provides easy retrieval and auditability for its users.
Using the data in the system, it is also possible to create complete documentation instantly, supporting indirect monitoring of project progress.

Further system integration to further build the platform

The consortium will continue to develop the platform, with plans to seamlessly exchange data between quality control measurements and digital models. This will be achieved through integration with the building materials laboratory.

The developers' long-term goal is to replace paper documentation with a modern, digital quality assurance platform.

This will help to increase efficiency in current processes and, in the longer term, prepare the construction industry for regulatory and technological changes.