Southern Circular Railway: spectacular photos of the bridge construction over Szerémi út and tram 1
The assembly of the right abutment of the railway bridge over the Szerém road is in its final stage, but all the bridge elements are now on the assembly area on the abutments. The complete bridge, assembled on site, should be in place by mid-April. The project is part of the Southern Circular Railway, a milestone in the history of Hungarian railway development, the first of its kind in the capital city for 100 years
– briefly summarises the background to the news item by investor Építési és Közlekedési Minisztérium (ÉKM). Our newspaper recently published a comprehensive annual summary at the beginning of 2025, which reveals that the general contractor for the current phase is V-Híd Zrt., while the plans required for the construction are being prepared by Kontúr Csoport Kft.. The project is being implemented with significant EU support from multiple sources.
The bridge is scheduled to be in place by mid-April
As explained in a recent statement issued by the Ministry, the last pair of bridge timbers arrived this week, so all ten bridge elements are now in the assembly area on top of the abutments. The bridge assembly area has been built on top of the final embankment retaining wall constructed on this stretch, so that the bridge assembly does not involve any additional land use or traffic restrictions.
The elements weigh 10-17 tonnes each, are 6.7 metres wide and 3 metres high. They can only be transported flat as oversized loads. The delivered elements are lifted by a 200 tonne crane to the assembly area where, after precise alignment, the next steps are the on-site fitting (using on-site welding technology), corrosion protection and the insulation of the bridge structure.
It is expected that the complete, locally assembled bridge over Szerémi út and tram 1 will be in place by mid-April.
Two new railway stations to be built
They go on to explain in detail: the Southern Circular Railway is one of the most important investments for the transport of the capital and the country, but its importance goes beyond that. It is a complex, 21st century urban development project that will renovate and extend the rail link between Ferencváros and Kelenföld railway stations and create a major green corridor from the Danube to the Buda Hills.
Three European Union rail corridors involving Hungary also run along this route. As a result of the project, two new railway stops will be created in the area of Közvágóhíd and Nádorkert, and railway capacity will be significantly increased.
The track will be extended to three and four tracks
The creation of three or four tracks instead of two, and the construction of new stations, will dramatically increase the suburban and urban performance of the railways, while the green spaces created will improve air quality and provide natural habitat for wildlife.
Source: Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November