What is being built?
A new transformer station surrounded by green space and decorated with porcelain was inaugurated next to BudaPart
E.ON Hungária Csoport has delivered a renewed transformer station in Kelenföld. Equipped with state-of-the-art remote-controlled equipment and smart devices, the facility provides electricity to almost 29,000 residential customers. The green-roofed building blends perfectly into the urban environment, with landscaped community spaces and a façade of almost 5,000 porcelain and glass insulators, according to the company's press release.
The development of the substation, which will cover thousands of square metres, aims to address the region's increased energy consumption needs, increase security of supply for people living in the South Buda regions and ensure the integration of weather-dependent renewable energy sources into the grid.
The HUF 3.4 billion project was implemented with the financial resources of the Instrument for Recovery and Resilience (RRF), pre-financed and supported by the Hungarian government, in cooperation between E.ON and Kopaszi Gát Zrt., which contributed almost HUF 1 billion to the development.
The Hungarian energy network is constantly being improved
The statement recalls that E.ON Hungária announced in January this year that it would launch a series of multi-year network development programmes worth around HUF 74 billion. The main objective of the investment is to promote the connection of weather-dependent renewable energy sources, in particular solar panels, in the northern and southern regions of Hungary and in Pest county. As part of this series of developments, the Kelenföld substation, which has been redesigned not only in terms of its technical content but also in terms of its appearance, has been renovated and is now a modern, urban environment.
"Electricity is the energy of the future. The new development will increase security of supply in the fast-growing South Buda region and further improve the quality of energy supply through modern technology, digitalised devices and smart solutions."
- said Géza Nagy, managing director of ELMŰ Hálózati Kft., part of E.ON Hungária Csoport.
The transformer station, which used to consist of several separate parts and was surrounded by a fence, was rebuilt in parallel with the development of the BudaPart district.
In response to the proximity of the new housing developments, the facility has been given a modern, aesthetically pleasing exterior: around 5,000 porcelain and glass insulators adorn the walls of the substation, and it is surrounded by a sledding hill, dog run and community garden for the neighbourhood. A green roof of 252 square metres of special vegetation has been installed on top of the building.
The fifth largest public park in the capital
"This investment points to the future by turning a technical artefact into an artefact of artistic value. But perhaps even more importantly, we have freed up industrial land that was previously closed off. With the dreamed park around the building, a high-quality area of more than 7000 m² has been created, providing not only the residents and office tenants of BudaPart, but also all citizens visiting the district and even the city, with the high-quality recreational facilities that are already familiar in BudaPart, voted the world's best urban district development last year. We are proud that the newly opened green space is the fifth largest public park in the capital - with a dog run and a community garden. By comparison, it is bigger than the Tabán or Városmajor area" - said Tamás Fodor, CEO of Kopaszi Gát Zrt. Development.
The substation, located in the 11th district of Budapest, will serve the increased energy needs of 29,000 residential customers in the South Buda region, as well as the businesses and institutions operating in the area.
Technical characteristics of the transformer station
The substation has 9 transmission line connections at 132 kV high voltage and two 132/11 kV 63 MVA transformers with a total weight of 188 tonnes. At medium voltage 11 kV, an indoor encapsulated switchgear was installed, with 46 consumer outlets and one busbar disconnector.The latter is automatically activated in the event of a major fault and reduces the number of customers affected by the fault without human intervention, thus increasing operational safety.The 11 kV switchgear, as well as the protection automation and auxiliary equipment required for the station, are housed in a switchgear and control room building with a floor area of more than 1200 m².
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November