SWIETELSKY built the new Nyíregyháza nursing home in one year
The construction of the new nurses" residence in Nyíregyháza has been completed. The three-storey building, located on the grounds of the Jósa András Teaching Hospital, was constructed by SWIETELSKY Magyarország Kft. With an investment of more than HUF 1.4 billion from the Human Resources Development Operational Programme, the living conditions of healthcare professionals will be significantly improved, with a total of 118 beds available in 60 mini-studios.
Attila Szűcs, Director General of the Szabolcs-Szatmár-Bereg County Teaching Hospital at the closing event said: the development was carried out under the direction and supervision of the National Hospital Directorate General (OKFŐ), and with the full completion of the internal works, the building will be ready for use by the end of the year.
The hostel will be used mainly for nurses, but will also accommodate other colleagues, residents and young professionals with families, who will enjoy comfortable, high quality accommodation at very good value for money, the Director General added.
The finishing touches were completed on time
The new block was built on the site of the old Infectology building, with a total net floor area of 1919.55 m2 on 3 levels. The contractor was responsible for the construction of the nurses' accommodation building and its connection to the existing building services, high and low voltage systems of the hospital.
The works started in August 2022 with the demolition of the old building, and the technical handover - acceptance procedure will start on 28 September 2023. The last days were spent on the final stages of the construction: furnishing the rooms, testing the installations, painting and repairs to the tiling, cleaning. The area around the building has been tidied up, the paving has been restored and landscaping has been carried out," said Csaba István Váradi, project manager of SWITELESKY Hungary Kft..
Laundry facilities on each floor
The load-bearing structure of the building is of longitudinal diaphragm design, with reinforced concrete columns. The apartments are comfortably designed and open from the corridor along the longitudinal axis of the building, on both sides. On all three floors there is a laundry room for the needs of the residents and a switch room. The ground floor has a separate reception room with a rest area, while the mechanical space is located under the staircase.
Comfortable rooms await their occupants
The building will have 58 2-person room units and 2 1-person handicapped room units, accommodating 118 people. The 24 m2 mini-guest rooms have bathrooms with shower, toilet, washbasin and towel dryer radiator.
In the living area there is a kitchenette with sink, fridge, hob and cupboards, as well as a wardrobe with a desk. Storage is provided by spacious built-in cupboards. Internet and television connections are available in the rooms.
All the rooms can be cooled and heated if necessary via a heat exchanger on the roof, and the heating is connected to the hospital's existing district heating network.
The implementation started with unexpected challenges
As project leader Csaba István Váradi said, the demolished Infectology was built in the 1960s, and its plans were no longer to be found.
"During the demolition works, the new building had to be demolished to an unplanned depth and then the foundations were laid. This, unfortunately, was also the case for the utilities and all other structures not visible in the ground, due to the unavailability or partial accuracy of the data."
He added: "The construction was further complicated by the fact that the works started after the Covid epidemic and the outbreak of the Russian-Ukrainian war. Both of these factors had a major impact on the deadlines for the delivery of materials, the procurement of construction materials as planned and the finding of suitable contractors."
Nevertheless, SWIETELSKY completed the project within the timeframe agreed in the contract, including the modifications and additional works ordered during the construction period.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November