Construction of the Hungaroring is underway at a fast pace - a spectacular video of the work site

Published

Despite the winter and the wet weather, work is still in full swing at the Hungaroring. Contractors Market Építő Zrt. and Bayer Construct Zrt. are racing against time, as there can be no unfinished buildings on the track during the mid-July race. At that time, the track will be temporarily restored to a race-ready state to allow the Hungarian Grand Prix to run smoothly. The full renovation of the Hungaroring will be completed in 2026.

Spectacular drone footage of the second phase of development of the Formula 1 race track in Mogyoród was posted on the YouTube channel of Hungaroring YouTube channel, which was also shared by Market Építő Zrt. on its social media page. The next phase of the Hungaroring refurbishment work began at the end of December, carried out by Market Építő Zrt. and Bayer Construct Zrt.. In just a few weeks, the two companies' experts moved 20,000 cubic metres of earth and broke up 5,000 cubic metres of concrete.

In addition, 800 piles have been drilled, the first tower crane has been erected, and a total of 345,348 kg of reinforcing steel has been delivered to the construction site to date.

 

 

The 10,000-seat main grandstand is renewed

As we previously reported previously reported, in April 2023, the government made a decision on the development of Hungaroring. In the first phase of the work, public utilities and infrastructure will be modernised to meet the requirements of the International Automobile Federation (FIA).

In the second phase, the consortium of Market Építő Zrt. and Bayer Construct Zrt. will renew the 10,000-seat main grandstand, the main building and the paddock, and build two pedestrian tunnels - one for competitors and sports staff, and the other for guests.

The development will see the demolition of the main building to make way for a modern, cost-effective and sports-oriented new main building. It will include 4 technical boxes and 36 competition boxes, with a competition control centre, catering and VIP areas attached to the main building, and an extension to the paddock area.

 

Racing against time

The timing of the works is of paramount importance, as the agreement with the Formula 1 rights holder stipulates that no unfinished buildings or construction-related activities can take place on the Hungaroring during the races.The Hungarian Grand Prix has a contract to host the Hungarian Grand Prix until 2032, and this year the Hungarian Formula 1 team will visit Hungary between 19-21 July.

Hungaroring to be completely renovated for its 40th anniversary

Based on the coordination of the construction works and the race schedule, the main grandstand and the event area will be renovated and the paddock area will be extended for the 2025 Hungarian Grand Prix, with a special focus on the smooth running of the Hungarian Grand Prix. The complete renovation of the Hungaroring is scheduled for completion in 2026, the track's 40th birthday. 