Three side-by-side finishers paved the wearing course on the Hungaroring finish line, 620 river metres in length, for a total of 8866 square metres.
An important phase in the modernisation of the Mogyorod racetrack has been completed: in a few months' time, the target will be filled with racing cars.
The last element of the roof structure of the main roof on the Hungaroring has been removed, and we show an extraordinary video of it.
Half of the new steel roof structure has already been completed by the consortium of Market and Bayer Construct.
The heavy steel structure of the roof will be built in four months by a consortium of Market Építő Zrt. and Bayer Construct Zrt..
In the last period, 20,885 cubic metres of concrete and 4,793 reinforcing steel have been installed in the two buildings by contractors Market Építő Zrt. and Bayer Construct.
The first stage of the Hungaroring's refurbishment has been recognised by the International Automobile Federation (FIA) and F1 officials. They asked the professional staff of the Mogyorod track to share their...
To meet deadlines, work was often carried out 24 hours a day, with 400-500 people working on the site at any one time, and a total of 1500 people working on the project.
The biggest of the many challenges is squeezing work between racing seasons in the large-scale development of the Hungaroring, which is progressing on schedule with the Market Építő Zrt....
Despite the winter and the wet weather, work is still in full swing on the Hungaroring. The Market Építő Zrt. and Bayer Construct Zrt. construction...