We asked Péter Badar, Épszerk-Pannónia Invest Építőipari Kft.'s site manager, about the construction of the unique practical training centre at Semmelweis University.

Alajos Hauszmann also stands out among the outstanding Hungarian architects of the 19th century with his public buildings. Although he is best known for the rebuilding of the Palace of Buda Castle, his name is also associated with the design of countless schools and hospitals, especially in Cluj Napoca and Budapest. With their iconographic features, brick facades and semi-circular shutters, the strong symmetry of the facades has become a natural part of the capital's skyline. A typical example of its public buildings is the former Institute of Forensic Medicine at 93 Üllői út, which will soon be converted and a new wing built to house the new innovation centre of Semmelweis University.

The development related to Semmelweis University's Institute of Pathology II will involve the partial renovation of the pathology institute and the construction of a new building, the National Medical Innovation Training Centre (NOIKK). The construction project, carried out by WEST HUNGÁRIA BAU Kft. construction project, Épszerk-Pannónia Invest Kft. is working as a structural subcontractor. The reinforced concrete structure of the new building will reach its highest point in the coming days, so on the occasion of the topping-out ceremony, we asked Péter Badar, the project coordinator and construction manager of Épszerk-Pannónia Invest Építőipari Kft., about the challenges of the work.

At the service of practical training

As stated in Semmelweis University's development plan, "NOIKK will unite the triple unit of education, patient care and research at Semmelweis University in a unique way, both in Hungary and internationally."

According to the plans prepared by Fusion Architect Kft., the new building, with a total net floor area of nearly 7,000 square metres, will be a -3 parking level + ground floor + 6 floors, with a flat roof, while the existing pathology building will be a -1 + ground floor + 4 floors high, high-rise facility. The two will be connected via the lobby and a passageway on level -1.

They are already building the end slabs

"At the moment, one of our main tasks is the construction of the end slabs, which, as we learned from Péter Badar, are unique in that they are designed with a one- or two-way slope. In addition, we are working on the construction of the 15-centimetre thick, straight-edged stairs in the corridor of the building, which are almost 10 metres long and form steps from below.

Other than that, we have completed everything on the main building: the outdoor pedestrian and car ramps, the curved-walled plant box, the soil sampling pit and the ventilation shaft." Concrete work is currently underway inside the building.

This has allowed the construction of the neck core to begin: the two structures will be connected by cutting through the diaphragm wall and by a carefully designed and constructed dilatation connection. "The piles are currently being cut back, after which," he said, "the steel reinforcement of the base beams will be installed, shuttered and concreted." The structural construction is, of course, closely linked to the waterproofing work, as both buildings require the contractor to meet dust-proofing requirements.

Special formwork and prefabrication also helped the work

"The monolithic reinforced concrete wall to be built next to the adjacent building, which had to be solved using single-sided masonry and very careful concreting, caused some excitement," explains the chief engineer of the facility. All this over six levels, and in addition, the fire wall in the attic of the adjacent building was only about 15 cm thick, so we had to take extra care to tie the formwork and support the brick wall.

The ÉPI is a Peri Skydeck slab formwork system for the construction, which enabled them to complete the formwork and stripping of the slabs extremely quickly and efficiently, with minimal material consumption.

They were also able to make the construction of the four-arm staircase extremely efficient by using stair arms they made themselves, with a total of 31 stair arms installed from the lowest level of the parking lot up to the sixth floor.