What is being built?
Fast and accurate work with prefabricated structural elements
The North Storm C Real Estate Development Sub-Fund is building a condominium in a very popular part of Zugló, a few blocks from the main transport routes, but on a quiet street. Magyar Ingatlanberuházó Zrt. is responsible for the implementation of the investment, commissioned by the Sub-Fund. The eight-storey (basement, ground floor and six upper floors) apartment building with 160 flats, which is being built at 32 Angol Street, has a varied façade and a subdued scale. 160-apartment condominium, is being carried out by Épszerk-Pannónia Invest Építőipari Kft..
Halfway to success
The building will consist of two dilatation units: a street wing will house the staircase and the elevator core, while the inner courtyard wing will be used only for apartments, without a separate vertical transport system. The structural works, currently at 50 %, are due to start in November 2023 and the contract stipulates that the roof structures should be completed by the end of September 2024.
"We are on schedule on Building B and have gained a significant advantage on Building A," Imre Nagy, Chief Facilities Engineer, told us.
The basement and ground floor structures on both parts of the building are now complete. In building A (courtyard wing) the reinforced concrete structures on the 2nd floor are being built, while in building B (street wing) the first floor structures are being constructed.
Excellent timing is needed
The complete reinforced concrete structural work for Zugló's newest residential building, with an A+ energy rating, is being carried out by ÉPI, including the installation of prefabricated panel walls and prefabricated stairs, as well as the installation of lightning protection and earthing systems in the monolithic reinforced concrete structures. Main quantities of the construction work:
- 26.600 m2 zsalu,
- 6.215 m3 concrete,
- 760 tonnes of reinforcing steel.
The colleagues at ÉPI are working with tried-and-tested large-panel formwork and aluminium floor formwork systems, and prefabricated shell panels are being erected next to the two adjacent firewalls. Prefabricated stairs will be installed in the stairwell, which are being manufactured by the contractor at its own prefabrication plant in Ercsi. A particular challenge during construction was the need to reinforce the foundations of the two adjacent buildings, which was carried out in several stages.
"We needed to work in harmony with the earthworks contractor on a daily schedule," the chief engineer stressed. "Coordinating the placement of the cooling-heating panels in the slabs is another additional scheduling task, in addition to the slab formwork, iron installation and electrical protective piping work in the slabs. Another interesting aspect is that the structural works have to be carried out with a crane, so particular attention has to be paid to organisation, including the scheduling of material deliveries."
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Bound track 2026. 10. 08.
Déli railway station is set to undergo a major refurbishment, paving the way for double-decker trains