What is being built?

From school to children's hospital

Published

The fourth phase of Épkar has been completed: the Újbuda Children's Health Centre has been inaugurated.

In the centre of Újbuda, one minute from Móricz Zsigmond Körtér, behind the clinic, stands a beautifully proportioned former school building with split ribbon windows and red brick cladding, which was completely renovated to create Épkar Zrt. Újbuda's newest healthcare facility.

At the end of 2018, a tender was published for the development of the Újbuda Children's Health Centre and One-Day Surgery in the modernist school building at 3-5 Kőrösy József Street, for which a contractor was sought for its complete renovation, conversion and extension. The plans for the facility, which will be able to treat 85,000 patients, were drawn up by Archikon Építésziroda, which is based in the district and has been involved in numerous prestigious projects in Budapest, drew up the plans for the facility, which will be able to treat 85,000 patients and will serve children from Districts XI and XXII as well as those from Érd, Diósd, Biatorbágy and Törökbálint.

Épkar Zrt. in Újbuda, the largest healthcare development of the last two decades, was created in 2010, but only in 2017 the transformation of the former school building could be started with the help of state funding, municipal and capital city resources.

 

Decades of plans realised

The complex will include 23 paediatric specialities, a GP surgery, a day surgery, an infectious diseases department, on-call rooms, a so-called shock treatment centre, where children in life-threatening condition can receive ambulatory care until the ambulance arrives. In addition to specialist care, the Children's Health Centre will also have a play area, hydrotherapy and child psychiatry.

 

A modernist building enriched with contemporary elements

In four phases, Épkar Zrt. was able to convert the former two-storey school building, which originally had a basement. By demolishing the gymnasium wing, the contractor had to carry out the structural reinforcement of the remaining building, with a total net floor area of 2348.6 m², and the addition of a net floor area of 618.6 m², in addition to the internal alterations and the complete energy renovation. This involved

  • in phase 1, the demolition of the gymnasium wing and the necessary structural reinforcements, the construction of the entire supporting structure (lift shafts, stairs, angular shafts, base reinforcements), the construction of the new building level facade and the thermal and water insulation of the building were completed.
  • A 2. In phase 2, partial architectural interior construction of the entire building (basement, ground floor, two floors and the new third floor), utility connections, complete electrical network (structured IT, voice, patient call, etc, intrusion detection, CCTV, access control, intercom), complete mechanical network (staircase heat and smoke extraction and fire dampers, boiler, radiators, circulators, air conditioning, wash basin, toilet bowl, shower tray, hand wash basin).
  • In Phase 3, the entire interior was built, the entire electrical network was installed and the entire mechanical engineering, plumbing (pool engineering), the entire fire protection system and fire alarm system, landscaping and the construction of the elevators were completed.
  • In Phase 4, the interior of the same-day surgery on the third floor was designed in architectural, mechanical and electrical terms, with the installation of a medical gas storage tank in the courtyard, the medical gas, water mist extinguishing, fire protection and fire alarm system on the third floor.