Operational tests in the new internal medicine block of the Székesfehérvár hospital will start in the summer
Work is proceeding according to schedule both inside and outside the new internal medicine building complex at Szent György University Teaching Hospital in Fejér County. Our portal has been reporting on the progress of the construction work from time to time here.
All specialist work on the new building will soon be completed, according to Szabolcs Cser, project manager of Fejér-B.Á.L.. The hot and cold coverings have been installed and the patient rooms have been painted. In the next phase of the interior design of the building, in addition to the electrical and mechanical installations, the built-in furniture will also be installed.
The connecting corridor will be renewed while ensuring uninterrupted patient transport
Construction will continue with the reconstruction of the corridor connecting the old and new buildings. Here the original steel supporting frame will be retained and new, custom-designed, state-of-the-art windows and doors will be installed. A cooling and heating system will be installed in the corridor, and the new part of the building will be clad and painted.
The renovation work will be carried out in such a way as to ensure the uninterrupted transport of patients and the movement of personnel necessary for the daily operation of the hospital in one half of the corridor. Parallel to the renovation of the passageway between the two buildings, the south-western façade of the new wing will be completed and the metal structure of the canopy will also be constructed.
New parking lots, sidewalks, perennial plants in parks
Landscaping work has already started around the new hospital block. An internal car park will be created in addition to the construction and restoration of roads and pavements. The contractor will also modernise the park, where sun and shade-tolerant flowers, shrubs and trees will be planted.
Operational tests of the building will start in the summer
The next major milestone of the project is the planned operational test, which will start in July.
All this indicates that the new 112-bed hospital complex, whose foundation stone was laid in March 2022, will soon be able to fulfil its healing and health-preserving function.
The building, which has a floor area of almost 6,100 square metres, will house the internal medicine department, the pulmonary department and will also be used for the treatment of cancer and infectious diseases.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November