What is being built?
The newest residential complex on the southern shore of Lake Balaton will be built from prefabricated elements
The apartment building in Balatonmáriafürdő is constructed from prefabricated elements of the Leier prefabricated elements in Balatonmáriafürdő, constructed by Perfect Steel System Kft. based on the plans of L Stúdió Kft.. As its name suggests, Part Lakópark is being built on the shore of Lake Balaton, in the central part of the town, close to the beach. The Győr-based company B. M. I. .L. Kft. investment, a 29-apartment condominium will be built in the first phase, followed by four more condominiums in the same location. We obtained the details from the contractor and the manufacturer.
The investor has been building with prefabricated elements for more than ten years
As a prelude to the project, the head of the Leier Hungária Kft. precast reinforced concrete structures business unit said that it was decided at the design stage that the five-building residential complex would be built using precast elements once completed. "The use of prefabricated elements of Leier was not new to the designer and the investor," said Gábor Takács, explaining the background to the decision to use Kft. and L Stúdió Kft.. "The cooperation between the three companies goes back more than 12 years: during this period, hundreds of homes have been built based on similar design concepts."
He explained that one of the main design considerations was that the buildings should be of high quality, yet economical and fast. "In the Balatonmáriafürdő complex, five-storey buildings will be created, taking advantage of the benefits of prefabrication on all five levels."
Next year the first building will be handed over and the next one can start
The managing director of the contractor, Perfect Steel System Kft., told our newspaper that preparations for the project began in November 2023. „We completed the foundations for the building at the end of 2022,” revealed Gábor Papp. „The project actually started at the beginning of March 2024, when the first elements were put in place.”
He added that the handover in its finished state is expected by September 2025; the other four condominiums will be built using the same technology and design. "We are in continuous negotiations with the investor about the continuation of the project: according to the preliminary plans, the construction of the next building "B" will start in 2025," added Gábor Papp.
The pace has accelerated, the need for live labour has decreased
The managing director pointed out that this was the first project where prefabricated elements were used, so they were interested in the task. "The Leier helped, and the fact that our project manager colleague had already worked with such elements within the company also helped, so the preparation and construction progressed smoothly and easily."
In response to our question, he said that they are also satisfied with the products and the related services. "The manufacturer reacts quickly to customer and contractor needs and modifications in logistics and during construction, and communication is continuous," said Gábor Papp.
Among the advantages he experienced thanks to the prefabricated elements, he highlighted the speed. "Today we are already pouring the concrete for the 3rd floor slab, which means that our building is being completed even faster than the previously agreed schedule, which is a benefit for us and the investor. In addition, the number of manpower required is much lower than with other technologies."
Thanks to the thin wall construction, a space fit for an apartment was created
We asked Gábor Takács, Leier Hungária Kft. precast concrete elements business unit manager, about the precast elements used in the construction of the apartment building in question. He pointed out that the 20 cm thick bark wall of the external wall structure with its 25 cm thick polystyrene insulation has an outstandingly good heat transfer coefficient of 0.15 W/m²K. "The internal wall structures are also made of 20 cm thick bark wall, and it is important to note that the wall thickness, which can be considered thin, also meets the required airborne sound insulation value of 56 dB," he added.
He also revealed that the use of thin wall construction has resulted in a total of more than 50 square metres of extra living space, equivalent to the size of an apartment, compared to if the building had been made of 30 cm thick ceramic masonry.
Four bark slab panels can cover an apartment
In the Balatonmáriafürdő project, in addition to the wall structures, the pillars and cornices, which define the unique architectural design of the building, are also made of prefabricated elements. "Here, the uniform products have not only facilitated manufacturability, but also greatly simplified construction," he pointed out.
The specialist made a special reference to the slab structure, which is made with Leier bark slabs, already considered traditional. "A total of 4-4 panels can be installed to cover an apartment. The balcony slabs are connected to the building with Schöck thermal bridge elements professionally installed in the bark slabs at the factory, which allowed a thinner slab thickness to be achieved than if the balcony slabs had been wrapped with thermal insulation."
According to him, prefabricated lintels above patio doors and prefabricated lintels to match the formwork design are also an integral part of the prefabricated building concept. "A multi-storey building cannot be built without staircases, so naturally they are also incorporated as high-quality prefabricated elements," adds Gábor Takács.
Another successful example of the spread of prefabrication
The branch manager indicated that the building will be equipped with a lift, in line with today's needs and legislation. "Here, too, it was important that the reinforced concrete walls of the lift should be as thin and precise as possible: they are made of 15 cm thick, solid, prefabricated reinforced concrete walls. A further important detail is that the elevator shaft and the partition walls and slab are acoustically isolated, so that no sound from the elevator is transmitted to the structure."
He concluded by saying that the project is another successful example of the 21st century construction industry's move towards prefabricated technology.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
