What is being built?

Community hidden in a landscape

Published

The Leier and Peikko products were used to make the construction of the new event space in Badacsonytomaj weatherproof.

In picturesque surroundings, in the centre of Badacsonytomaj, adjacent to two villa buildings, stands a steep, longitudinal plot with an average transverse elevation of four metres, on which three commercial premises and the town's new event venue can now be built as part of a private investment. The vineyard-surrounded environment is constantly being beautified, which the contractor Vértes-Út Kft. is doing with the products Leier and Peikko products, according to the plans of Tamás Vadász and Márk Havanecz (AÁB Generál Kft.).

The concept evolved from the idea of a cellar row, the aim of which is to give smaller wineries the opportunity to present themselves in a prominent location, to reinforce each other and of course to share wine with other winemakers.

Community events also required a space that could accommodate larger events. So they were looking for a contemporary reinterpretation of the cellar row that would fulfil its function with as few gestures as possible and without ostentation. A simple rhythm has been given to the building, which is carved into the hillside, and the use of materials and scale was intended to respect the environment, while the roof of the building is covered in greenery and hides in the hillside. Its plan follows the same rigidity: each opening has its own access, but is connected and unified by a common porch.

Prefabrication helped the construction

Gábor Takács, the manager of the Leier precast reinforced concrete structures business unit, informed us about the products used. According to this, the contractor is using Leier bark slabs for the reinforced concrete wall structure, while Leier hollow slab balls and Leier Mesterpanel slabs are used for the slab structure.

"The rapid construction of the prefabricated elements helped the construction process, so the bad weather did not affect the deadlines. We started construction on 27 November and on 13 December we delivered the slabs, by which time the monolithic piers were completed and the Peikko Deltabeam beams were in place," said the branch manager.

The constraints of the exterior height of the new building, which is largely below ground level, and the need to create the most spacious interiors possible led the designers to use prefabricated elements. The Peikko slab beams were chosen to complement the Leier products, as the aim was to provide a solution where the precast slab could be built easily, safely and economically while minimising internal height.

"Two Deltabeam types were chosen for the project: eight-metre, 2.3-tonne beams D37-500 and 12.5-metre, 4.3-tonne beams D45-600 to support the precast slab. They were dimensioned and fabricated in the Peikko factory in Slovakia (Vágkirályfa) and manufactured in the Peikko factory in Romania (Bucharest)"

- we learned from Adám Takács, sales engineer of the Peikko. For easier placement and to reduce the number of supports under the slab, the connection of the pillar-Deltabeam beam was secured with HPM studs. "The final deflection of the over-tensioned Deltabeam beams reaches its maximum value when the slab is loaded," he added: "Under the slab with 50 mm of concrete and circular planks, the deflection of the beams is only between 105 and 250 mm.

With the solutions in place, design and construction have become faster, safer and more efficient!"

Source : Link

Popular