What is being built?

The new Rossmann logistics centre in Anvil was completed in record time

Published

Rossmann
In the 28,000 square metre warehouse, the construction of the nearly 4,000 square metre, 3-storey semi-automatic warehouse technology is already in full swing.

The Rossmann drugstore chain has expanded its supply chain in the Budapest metropolitan area with an investment of nearly HUF 20 billion: the 28,000-square-metre facility built in Üllő reached its current state of readiness in just 11 months – we wrote about the investment at the time of its launch written about the investment. Work has begun on the new centre's system technology (spanning three floors and nearly 4,000 square metres) after the developer Panattoni Hungary and the owner, OTP Ingatlanbefektetési Alap, handed over the facility under an early access agreement, according to a statement sent to our newspaper.

The general contractor is Goldbeck Hungária Kft., which has been present on the domestic market since 2016 and is known for the realisation of industrial and logistics facilities. The entire project and the associated 4,000 sqm modern office building are expected to be fully completed by the third quarter of 2025, with the move-in expected in early 2026.

High-tech logistics systems

Part of the facility, which is unique in the Hungarian commercial sector, was already inaugurated in November 2024, thus enabling the installation of the Pick-up Tower technology to start. This was also the time when the special industrial floor was completed, allowing the deployment of unique solutions for warehousing, such as the conveyor, PickByLight and Voice picking systems.

Daily reconciliation

"A project of this scale requires precise, coordinated work from all parties involved. We coordinate with the general contractor, the developer and the landlord on a daily basis on the design and construction process"

- said András Farkas, project manager of the Rossmann Magyarország Kft. investment project. He added: the selection of the interior design contractor for the office spaces is currently underway, followed by the preparation of the tender documents for the technological and operational documentation of the cooking kitchen.

A key project in the developer's Panattoni Hungary Development Kft. portfolio, the project received professional recognition during its construction: it won the "Real Estate Investment Transaction of the Year in Hungary" award at Portfolio Property Awards.

Source : Link