Modernisation of the infertile couples centre at Semmelweis University underway

Published

Photos: Épkar Zrt. / Facebook
The construction of the new section of the SE Assisted Reproduction Centre will be carried out by Épkar Zrt. in two phases, while maintaining the hospital's operations.

The construction of the operating theatre and inpatient ward of the Assisted Reproduction Centre in Building No. 30 of the Semmelweis University Clinical Centre is progressing well. The contractor Épkar Zrt. a few days ago photo gallery on its Facebook page.

As previously we wrote, the work must be carried out alongside the hospital's normal operations. The recordings show that mechanical and cladding work is ongoing.

Photos: Épkar Zrt. / Facebook

The contractor will have to carry out the 1.6 billion forint net development in two phases.The first phase will involve the construction of the ground floor works to provide outpatient care, which will be relocated from the second floor of the building to the ground floor once completed. The conversion of the basement and the upper floors can then begin. The total construction will involve approximately 2400 m2.

In addition, according to a separate schedule, and possibly at the same time as Phase I or II, Épkar staff could build new parking spaces next to the building. The contractor has 17 months to complete all the tasks involved.

According to the Semmelweis University website, after several years of planning and months of construction, the centre's outpatient clinic was officially opened on 11 October 2019, where the complex examination and care of infertile couples began.

The centre will be open to patients with full capacity and professional spectrum from 17 February 2020. One of its most important features is its ability to provide a full range of infertile couples' examinations in one place, without the need for lengthy follow-up.