What is being built?
SCHOTT Pharma expands production of pharmaceutical storage products in Lukácsháza – topping-out ceremony held for new SCHOTT hall
The purpose of the SCHOTT Pharma investment is to expand the existing factory by constructing new production and packaging units. The purpose of STRABAG is to construct the entire building structure: the construction of the clean room, the installation of building services, building electrical and building monitoring systems, as well as the design and implementation of the energy monitoring system. The work also includes the design, licensing and installation of the sprinkler system up to the technological connection points.
Construction in the embrace of stream valleys
The work area, covering more than 13,000 square metres, is located between two stream valleys on fine-grained, clayey soil. The clayey soil, which is prone to volume changes and has no drainage, required special flooring solutions.
During construction, a prefabricated pillar frame structure was built with floor slabs, reinforced concrete stiffening walls and staircase blocks. The foundation was constructed using CFA technology with drilled piles. The work area was secured with sheet metal barriers, and cabinet shafts were also used. During the earthworks, approximately 5,000 cubic metres of soil were excavated, of which approximately 400 cubic metres were used as backfill next to the foundation bodies.
The structure was completed in six months.
At the topping-out ceremony, the project participants – representatives of SCHOTT Pharma, designers, contractors and industry partners – looked back on the work done so far. Fabian Stöcker, head of SCHOTT Pharma's pharmaceutical storage solutions division, emphasised in his speech that it seemed like only yesterday that the foundation stone was laid, and now the project team can celebrate the completion of the structure.
As he stated, the structural readiness of the project demonstrates the preparedness and commitment of the professionals working on it. Emphasising the significance of the development, he said that more than one billion people worldwide live with type 2 diabetes or obesity, and innovative drug therapies, such as those containing the active ingredient GLP-1, are playing an increasingly important role in their treatment. The safe use of the latter requires world-class drug storage solutions, especially sterile cartridges, in the manufacture of which the new plant will play a key role.
In her welcoming speech, Britta Harder, project manager of SCHOTT Pharma, recalled the stages of construction work completed so far. She said that the past six months had seen the piling and erection of prefabricated structural elements, which was one of the most spectacular phases of the project. She expressed her special thanks to the professionals working on the construction site for their precise and safe work.
In her speech, Eva Szabó, managing director of SCHOTT Hungary Kft., emphasised that the completion of the structure is a milestone for the project, which is the result of perseverance and shared belief. As she put it, the facility is not just concrete and walls, but embodies a forward-looking development. She also emphasised that work safety was a priority during construction and that she is proud that the project has progressed without any accidents so far.
Complex implementation with clean room requirements
One of the biggest technical challenges of the project is meeting the extremely tight deadlines for external machine deliveries and complying with cleanroom requirements. This is because the new hall must be directly connected to the existing cleanroom-certified units of the operating facility.
Cooperation between designers and contractors
Sándor Ábrahám spoke about the concept behind the new factory building, saying that it is a special moment for an architect when the ideas expressed in the blueprints become a tangible building. The production hall was designed to connect seamlessly with the existing building, while providing a modern and sustainable industrial environment for future technologies.
The implementation of the project, he pointed out in his speech, was also facilitated by the effective professional dialogue that developed with the staff of the authorities involved during the licensing process.
The design process was coordinated by IN-EX Studio. Project manager Zsóka Máté said that during the one-year design period, an efficient and well-functioning professional team was formed. The topping-out ceremony is a celebration of the completion of the structure, in which the structural designers and the contractors who turned the plans into a real building played a prominent role.
Special attention is paid to energy efficiency – waste heat is also utilised
Energy efficiency also plays a key role in the investment. The building's energy monitoring system optimises the facility's energy consumption, while waste heat generated during technological processes is utilised through heat recovery systems.
Exemplary group-wide cooperation
Representing STRABAG, Imre Etl recalled that the tradition of the topping-out ceremony dates back to 14th-century Germany and marks the moment when a building reaches its highest structural point. As he put it, the current event is not only a construction milestone for them, but also a celebration of partnership. The success of an investment of this magnitude requires both the work of the professionals behind the drawing boards and the physical labourers who work day in and day out on the construction site in heat, snow, wind and rain.
One of the special features of the project is the close cooperation between the STRABAG group companies. Joint planning work at an early stage of the project made it possible to select technical solutions that are economical, cost-effective and quick to implement. Flexible daily scheduling ensures that implementation is aligned with the current progress of the project.
Partnership and joint performance
Several domestic companies are involved in the construction. Metál Hungária Zrt. is involved in the cladding work on the building. The company's business director, Balázs Heckenast, emphasised that for their employees, the topping-out ceremony signifies that the building will soon be under roof. As a Szombathely-based company, it is particularly important for them to be able to participate in a significant industrial investment in their home environment.
The building services engineers of Kozma Kft. are involved in the building services engineering work. Company representative Tibor Kozma said that his company has been working on mechanical systems for industrial facilities for more than thirty years. During construction, special attention is paid to occupational safety. István Debreczeni-Mór, managing director of Global Production Kft., said that they have been supporting STRABAG since 2017 and that their commitment to safety is unwavering.
He added: "The greatest joy for an occupational safety specialist is when they can work with their partners towards a common goal, which is to ensure that everyone can go home to their families at the end of the working day."
The factory hall may be handed over next year
The topping-out ceremony concluded with a joint lunch for the participants. In his closing remarks, Krisztián Kiss, technical manager responsible for the STRABAG project, emphasised that the current event marks the successful completion of the structural construction and represents another step towards the realisation of modern, high-tech manufacturing capacity.
The handover of the investment, together with the necessary certifications and the operating licence, is expected in the second half of 2027.
Source: Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure