Road building

One of the most important projects in the southern counties can start - the construction of the Mohács Danube Bridge

Published

The plans were ready by the end of last year, and now construction can begin: the roughly 28 km link between Highway 51 and the M6 motorway is a key stage in the interconnection of the radial motorways, which will finally see the construction of the Mohács Danube Bridge.

As reported in our newspaper, the detailed design plans for the Speciálterv Kft. have been completed by the end of 2022. completed with the implementation plans, so there is no longer any obstacle to the construction of Hungary's 22nd bridge, which will span the main channel of the Danube (20 bridges are already in place, and the 21st will be the bridge between Kalocsa and Paks, which is currently being built by Duna Aszfalt Zrt.). The locals have been waiting for this development for centuries, without exaggeration, but the bridge is also of particular importance for freight traffic, as it will relieve the bridge in Baja, and will also be a key element in the southern national expressway ring, as it will play a prominent role in connecting the radial expressways and the industrial centres of the cities near the southern border (Pécs, Mohács, Baja, Szeged).

Could be ready in 2027

According to the announcement of Építési és Közlekedési Minisztérium announcement, the investment will be implemented in three phases over approximately 50 months, with bids evaluated on the basis of the best price-value ratio. In the first phase, on the Alföld side, near Csátalja, a new, almost 20 km long, 2×1 lane road will be built (which can later be upgraded to a 2×2 lane motorway) from the 51 main road to Újmohács. To this end, a roundabout will also be built at the starting point of Route 51 and near Sárhát, while a four-arm level junction with a 2×2 lane, divided carriageway design may be built at Újmohács. The section includes

  • three road bridges,
  • one with six holes,
  • two two-supported artefacts,
  • and a cycle path leading off the new Danube bridge.

From Mohács to Újmohács

In the second phase, a bridge will be built to cross the Danube river, with two river bridges and a river bridge, totalling 756 metres in length. The structural system of the bridges is planned to be a two-span steel arch bridge with steel deck below deck, with closed box-section struts and arches, an orthotropic steel deck slab and a double-sided suspension with a grid arrangement. The overall structural height is 2.75 m, with the arches in a tilted configuration towards each other, connected by an X-grid cross-connection system. The Danube bridge will also be built as a 2×2 lane divided carriageway road with a cycle track overpass.

Source: Speciálterv

Getting to the motorway will be easy

In the third phase, a 2×2 lane divided carriageway road of 8.5 km in total length could be built from the bridge to the M6 motorway. The first part of this will be completed up to the existing roundabout junction of roads 56 and 57, 2.7 km along the existing municipal road, after its demolition. This section will also include a multi-lane structure over a public road and siding, a three-lane structure over siding, a two-lane structure over an industrial estate road and a cycle underpass. Also in the third phase, the current 2×1 lane road 57 will be converted into a 2×2 lane divided carriageway from the roundabout to the M6 motorway, which will be converted into a two-lane turbo roundabout, but will also include

  • three new turbo roundabouts,
  • three two-supported artefacts,
  • as well as a two-post cycling artefact.