Bridge construction work on the eastern border motorway is ramping up

Published

The four-lane road from the M3 towards Satu Mare-Moreti will also have to bridge the river Kraszna, among other things, for Duna Aszfalt.

Bridge construction on the M49 expressway project gained momentum on the first 15 km section, according to magyarepitok.hu. As we previously reported, the M49 road is being built as part of the Építési és Közlekedési Minisztérium investment between the M3 motorway and the Hungarian-Romanian border crossing near Satu Mare. The first phase of the development is currently being carried out by Duna Aszfalt Építő Zrt.: involves the construction of the first 28.15-kilometre section of the expressway between Mátészalka and Ököritófülpös.

In the year 2024, significant progress has been made in bridge construction on the first 15 km of the bridge section, with CFA drilled piling work starting on a total of nine structures. In addition, the construction of the structure, piles and piers is progressing steadily, and in April the girder construction started.

Bridge builders have already crossed the Krasna

We asked specifically about the work on the Kraszna bridge on the section in question. According to the reply, the construction of the bridge over the river is progressing on schedule, with the piling of the E span being completed, the steel main girders are being delivered and welded, and the auxiliary yoke structures are being installed.

The report said that the construction works had "crossed" the Krasna and that humus removal and subsoil stabilisation works had started between km 15+000 and 17+000.

Construction of the bypass road at Mátészalka has started

The summary also pointed out that, in addition to the construction of bridges, earthworks are being carried out with great vigour, as well as utility replacements and water works through the construction of culverts, canals and sewers.

The report also mentioned the construction of the Matészalka junction at the crossroads of road 471 as a particular challenge. This can only be done by diverting 900 metres of the 471. Construction of the bypass, including the cycle path, has also started. Once the bypass is in place, the construction of the Matészalka junction and the B075 bridge can start.

Of the separate level junctions, only the planned junction at the Járminál has so far started work: the embankment is already under construction, and the formwork and concreting of the supporting pillars has already begun on the associated bridge B017.