Road building

Almost a hundred sites upgraded in seven months

Published

A total of 480 kilometres of lanes on the M1, M15, M3, M30, M35, M4 and M7 were renewed by July this year.

More than 1.8 million square metres of ageing, deteriorated pavement on 98 different parts of the country were replaced with new asphalt by 1 August this year on more than 1.8 million square metres of national motorways operated by MKIF Magyar Koncessziós Infrastruktúra Fejlesztő Zrt., the company told MTI on Thursday.

According to the announcement, around 480 kilometres of the seven national motorways - M1, M15, M3, M30, M35, M4, M7 - have been renewed so far this year, including the lanes of several junctions and rest areas. This has involved the use of 300,000 tonnes of asphalt. In addition, 72 bridges and overpasses and 9 rest areas have been renewed across the country in the last four months.

Work on the M1 and M7 to be stopped in August to cope with heavy traffic

The biggest motorway upgrade in Hungary's history started in 2023 and will last until 2025.

This concerns 43% of the 1,237 kilometres of main line taken over by MKIF for operation, renewal and upgrading, i.e. 538 kilometres. Over the 3 years, 200 bridges and flyovers will be renewed, and the drainage systems and possible gullies of 50-60 junctions will be repaired.

In 2023, 19 percent of the main track was replaced with new asphalt, replacing and repairing not only the wearing course, but also the underlying binder course and deeper structural parts where necessary. By the end of this year, another 20 percent of the main track is scheduled for renewal, the statement said.

It was pointed out that in August, due to increased transit traffic on the M1 and M7, there will be no asphalt works planned at all in either direction. And on the M7, there has been no work on the M0 towards Lake Balaton between Balatonvilágos and the M0 since the start of the holiday season.