The renovation of the Flórián Square flyovers can start soon - the contract has been signed

Published

BKK
The KM Építő Kft. project will start in the first quarter of 2025 with the upgrading of the structure connecting Szentendrei út and Árpád bridge.

Work on the Flórián Square overpasses is one step closer to commencing: on 16 December 2024, the Budapest Transport Centre and KM Építő Kft. signed a contract on 16 December 2024, under which the contractor will carry out the modernisation for a net price of HUF 2.1 billion, according to a statement sent to our newspaper by BKK. The construction plans were prepared by FŐMTERV Mérnöki Tervező Zrt.. Technical supervision will be carried out by the staff of Budapest Közút Zrt..

The total project cost - including the mandatory reserve, the design fee, the technical inspector fee, the official fees and other costs - is expected to be around HUF 3 billion gross, including VAT. The reconstruction is expected to start in the first quarter of 2025 and to last until spring 2026.

 

 

Further delay would increase the damage to the structure

As we wrote in our previous article, the technical condition of the Óbuda overpasses, built more than forty years ago, has deteriorated significantly since the last intervention.

During the investment, the experts

  • the road surface will be replaced;
  • repair defects in the reinforced concrete structure;
  • the insulation will be renewed over its entire width, eliminating the cause of leaks above the pillars;
  • a new reinforced concrete kerb will be built, on which a new, safer guardrail will be installed;
  • a new expansion structure and anchorage will be installed at both ends of the bridges;
  • repair defects in the drainage system, retaining walls, bridge abutments and concrete surfaces of piers, and
  • special attention is also paid to the integrity of archaeological finds.

 

The modernisation of the flyovers will be carried out in two successive phases

The two parallel overpasses connecting Szentendrei út and Árpád Bridge ensure the passage of more than 50,000 vehicles per day: it plays a key role in the traffic of Budapest and the agglomeration, as it connects transit routes that cross the border of the capital.

During the works

  • from Szentendrei út Traffic to Pest separate level of passage is planned to be guaranteed at all times, while
  • traffic from Pest in one phase it will run on a separate level on the flyover, and in the other phase it will turn underneath to Szentendrei út.

The works will inevitably involve traffic restrictions and temporary changes, so BKK is asking people travelling from the agglomeration to use public transport during the renovation if they can, thus reducing the traffic load in the area. Exact details of closures, diversions and alternative routes will be provided by BKK before the actual start of the works.

There will be a short period during the works when the tram 1 service cannot be guaranteed under the flyover, during which time the BKK will provide the necessary bus replacement.

 

Billion-euro project with recovered money

The funds needed to implement the project, worth around HUF 3 billion gross, will be provided by the Municipality of Budapest. The costs are largely covered by the amount recovered in the marathon-long lawsuit related to the electronic ticketing system, which was concluded in early March.

As you know, following the decision of the International Court of Arbitration in the lawsuit brought by BKK against Scheidt & Bachmann in 2021, the German company will pay a substantial amount to the Budapest transport operator after it breached its contract as the contractor of the electronic ticketing system in Budapest.

Source: Link