Road building
The start of the M1 motorway extension is getting closer - temporary slip lanes are already under construction
We are back with another report on the preparations for the expansion of the M1 motorway, where the first phase will enter the main construction phase in a month and a half. Our newspaper regularly reports on this historically significant investment, and recently published a comprehensive interview with Tamás Németh, CEO of the investor MKIF Magyar Koncessziós Infrastruktúra Fejlesztő Zrt., the investor. Among other things, we received information about the preparatory work currently underway, as well as the fact that the actual expansion will begin on 1 September 2025 at the latest. MKIF Zrt.
The extension of around 80 km will
The road surface will be renewed from the M0 motorway to the Concó rest area in the Ács and Bábolna area, and the M1 will be expanded to 2×3 lanes + ITS lane (the latter abbreviation stands for intelligent hard shoulder).
Now, in a Facebook post preparing for the M1 expansion, MKIF reports that they will assist with a fast lane, as detailed at reports in its Facebook post preparing for the M1 expansion that MKIF will use fast lanes to help with traffic at junctions on the M1 during the expansion, so temporary ramps will be built.
These new, temporary roads will not only facilitate and speed up access and grading, but will also provide access to the M1 in places where existing junction branches would prevent the rebuilding of bridges and flyovers," they summarise.
During the expansion of the M1 motorway starting this year, 72 existing underpasses and overpasses will be rebuilt to meet the new cross-sectional requirements. The widened carriageway would simply not fit under them.
In the first phase, such temporary ramps will be built at 6 junctions. These are:
-
Concó,
-
Tatabánya,
-
Obarok,
-
Bicske,
-
Herceghalom
During construction, around 6,000 cubic metres of earth will be moved and more than 7,000 square metres of asphalt will be laid. The temporary roads will be built in 3 layers, with a total of 23 cm of asphalt, to cope with the load they will take during the expansion. The temporary roads will also use part of the asphalt that was previously laid.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure