Road building

M1 extension: how the motorway is being prepared for the widening of the embankment

Published

Photos: MKIF
The huge MKIF investment, which will add new lanes to Hungary's main motorway, will ensure 2×2 lanes throughout.

This week, main phase of the M1 motorway expansion, which has been in preparation for the past year. During the expansion of the M1, the section between the M0 and Bicske will be completed by 31 August 2028, and the section leading to the Concó rest area will be completed by 31 August 2029, after which the development will continue.

The work of MKIF Magyar Koncessziós Infrastruktúra Fejlesztő Zrt. project, the 78 km section of Motorway 1 between the M0 and the Concó rest area at km 94 will be expanded to 2×3 lanes, plus a so-called intelligent hard shoulder that can be used as a full traffic lane on each side. This will allow traffic to travel on up to 2×4 lanes between Budapest and Győr.

The widening of the embankment can start soon

As MKIF on Facebook explained, at present

  • the removal of vegetation from the inner dividing strip is ongoing at several sites;
  • the construction of temporary factory gateways and internal emergency shelters is ongoing
  • and the construction of intermediate supports for the bridges is also well under way.

These works are essential to allow for the new traffic regime expected to start in mid-September, which will already allow for the widening of the embankment.

Currently, all junctions and rest areas are freely accessible, with no restrictions. However, with the new traffic regime starting in September, there may be rest area and junction closures, but no two consecutive junctions are planned to be closed at the same time.

Up-to-date information on traffic on the M1 is available here: https://development.mkif.hu/m1. In its post, MKIF confirmed its earlier indication that the 2×2 lanes will be provided for road users throughout the widening.

Source : Link