"We're not looking for monotonous work - we're looking for exciting, unique projects"
Where we are now stood agricultural land nearly twenty years ago, began Róbert Lovas, director of the manufacturing division of Weinberg ’93 Építő Kft. production division. He continued: "Following in the footsteps of our industrial heritage, we purchased the former Malomkőgyár site, along with the surrounding farmland and family homes. The setting is magnificent, nestled in the Zemplén Mountains, which is why we pay special attention to our environment and environmental protection.
Ideas along the way
Since the beginning, I have been part of the Weinberg team. The first company project was a general construction project in Ócsa, for FÉG Konvektor Rt. we were able to build a new production hall. Our customers gave their trust to the company and to István Derczó, founder-owner and managing director of Weinberg, which gave us the opportunity to build the first reference project. Everybody gave their best to build a good reference building.
Initially, I managed building construction and organised production until 2015. The size of the company and its ability to stand on several legs allowed it to create two divisions. The development of business by division opened up new market opportunities in the company's development.
In 2016, we split our activities into two business areas, general construction and steel structures. From this year onwards, I have been managing the steel structures business of the company. When the manufacturing division was set up, we planned medium- and long-term visions, which we follow year by year and adjust if necessary.
Among our goals was the development of a manufacturing technology for double-curved steel structures and the production of bridge structures. Our expertise and technology allowed us to envisage positive and ambitious plans.
After the big plans came the realisation of dreams. With hard and persistent work, the steel structure of the Hungarian House of Music was undertaken and completed. This was preceded by the fabrication and installation of the curved pipe structure of the Haladás stadium. The company's technical capabilities were put to great use on these projects. The steel structures of the Hungarian House of Music, designed by the Japanese architect Sou Fujimoto, realise the spatial form of the buildings. These were followed by the Ethnographic Museum and the Multifunctional Hall in Tatabánya, where the unique steel structures were realized. Both projects were manufactured and installed by us.
Twenty-two years on the same road
The year 2002 was a milestone in the life of the company when the owner decided to build a new production hall. The new production hall was equipped for the manufacture of main supporting structures for buildings. The new building had a higher ceiling height and a híddarus material handling system.
In the hall, we installed a grit spreader, a heavy-duty saw and a 6.3-ton crane. Painting was finally done in a painting booth - of course, we now have a painting hall. And all of this reflected the fact that we knew what we wanted to achieve.
We set out to manufacture the main steel structures with strong support from the owners and young, creative engineers, with whom we have been able to put together a unique manufacturing technology for the Weinberg.
We had no past, but we had a present and we had a vision.
The technological development has brought results
In 2008, we decided that we wanted to use CNC machines to produce customised steel structures. As part of this development package, we purchased modern machining machines with CNC files. Our aim was to achieve more efficient production and the quality of workmanship provided by the machines. With the completion of the investment, the economic crisis of 2008 arrived. At that time István Derczó asked me: was it a good investment to build a machine park for the new direction?
At the time I wasn't so sure, but now I can say that it was a good decision to invest, as the new technical standard has helped us through a difficult period. Our competitiveness in the western markets has increased because of the mechanisation of production. The new CNC machining machines were there to reinforce our quality service. With this background it was easier to prove our suitability to new foreign partners.
The conscious choice of technology and machinery has made it easier to build new partnerships. For partner companies with similar activities, the level of contact has reached the level of file exchange production. What is file sharing? Our customers no longer sent us a design of the items to be produced, just a digital file package for the production machines. The availability of these enabled a short turnaround time.
The European market also pulled the Weinberg
When a foreign customer came here and looked around, he said: everything here is the same as in our factory, only it's in Hungary - and that's what drove us forward.
Opening up to the West has of course also brought us the way of thinking from there: that's why we perhaps operate a little differently than domestic steel structure manufacturers in general.
'Around 2010, we had a lot of foreign partners,' said the director on the walkway from the office building to the hall, 'and suddenly we jumped into a lot of different jobs, with some failures. We've ventured into many industries with different welded steel structural products. Sometimes we pushed our technological and capacity limits.
Today, it is the special tasks that drive the company forward
To my question - have you been working with the same approach ever since? - the first answer was with a smile, Róbert Lovas added: "We still have the courage, which also means that our colleagues in the production division have a poor tolerance for monotony.
It may seem strange to say this as a manufacturer, but even though we can serve the engineering industry and the building construction industry, we don't want to do monotonous work. If they ask for 10 of something, we're happy to do it, but we don't want hundreds. We are looking for custom orders.
We don't want to commit ourselves, we like the project approach because we like the challenge and the tasks to be done. We like to think in terms of projects, preferably individual projects. We're happy to produce double curved surfaces and similar difficult to build elements.
The company's service does not start when production begins, but before. Design and investment firms require professional communication on manufacturability for more complex tasks. This is our opportunity to share our manufacturing and installation experience with designers. When making our proposals, we can also back up our proposed technical solutions with machine simulations. By going round a project in this way, many sleeper problems can be avoided in advance. Of course, Weinberg is not a consulting company, but a manufacturer and contractor, so we like to manufacture, but if necessary we can also support other trades involved in the implementation.
The advantage of uniqueness
At Weinberg, know-how is combined with real creativity, and unusual and difficult tasks drive our progress. Achieving the unknown and difficult goal is a winding road that leads all project members through a steep and challenging, but beautiful professional arc.
We've always been open to development, whether professional or technological, and our colleagues are supported, giving them professional confidence, so we don't need to be afraid of change.
Consciously selected machines for superior quality
In 2017, based on customer enquiries and our level of professionalism, we decided to enter the market for both machined and welded steel structures. To put it simply, we are adding machining to our existing services, but it is more complicated than that. New material qualities are emerging, and the production technology needs to be understood. For chipping, we bought a Skoda FCW 150 horizontal milling machine with a nail head attachment. The working range of the machine allows the cutting of products up to 13 metres long at a height of 3 metres.
Although we didn't have the cutting capacity before, we now undertake the cutting of large and high-precision structures. It is worth mentioning that our cutting plant is air-conditioned. When it comes to the production of high-precision parts, the temperature variation of the raw material is a factor.
We have already turned steel structural elements of a double-frame building, as well as machinery structures and bridge elements. The precision of our machining has opened up new markets and projects for the company.
Sustainable steel structure manufacturing?
In 2008, we built the main office building of the hall. We decided to heat and cool the new building using alternative energy sources and not to pollute the environment. We installed a ground source system using water-to-water heat pumps to meet the building's needs. For our later capacity expansion and energy upgrades, we installed air-to-water heat pumps to serve the manufacturing plant.
We would not have got into the Scandinavian market, for example, if we were not demonstrably sustainable.
Environmental protection is very important today. It is not yet possible to decide whether economic or environmental considerations are more important. One thing is certain: while keeping sustainability in mind, environmental and sustainable production processes must be improved for the sake of the earth and our environment.
The domestic market is not yet looking for quality
There is insufficient market protection in this industry and insufficient external support. Foreign workers can easily enter and work in our country, putting domestic manufacturers in a difficult position. We cannot compete with companies that employ foreign workers. Just look at the Austrians: they only outsource to foreigners when there is no one left in the country to do the job - and they don't look at the price.
Once we've got a foothold, we'll stay in the western market, because it's not easy to get in. Because if you want to get to a Western European level, you need volume and quality, and as I see it, globalisation is forcing even the companies with volume to join forces. We mostly work with Scandinavians.
The steel industry for the future
Have you found yourself in the steel structure industry? - I asked the director towards the end of our interview. What I proposed - he summarised after some thought - was built largely unchanged. The assembly of the technological lines was largely based on my proposal. Our owner István Derczó was confident that the proposals put forward were marketable and, if implemented, would strengthen the market position and value of the Weinberg. To achieve the goals, a good team is needed, which takes ownership of the production capacities entrusted to it. There are also goals because we want to be proud not only of the results achieved, but also of the new challenges that await us.
Our main industrial objective is to promote the wider use of steel as a raw material that can be recycled in 100%. With the tightening of environmental criteria, we are confident that more investors or builders will prioritise steel as a material for their projects.
To implement this approach, a fundamental shift of emphasis is needed, where the economic aspect is not the most important, but the sustainability and ecological one. This must be a common goal, because we live on the same earth and breathe the same air.
We are no different from the rest, we just keep our eyes open, improve and do what our customers ask us to do. We can't solve the impossible, but what we can see the slightest hope for, we look into. That's how we got here.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about