Current at
The Hungaroring contractors have cancelled the schedule
The consortium of Market Építő Zrt. and Bayer Construct Zrt. is on schedule with the refurbishment of Hungaroring, according to a press event held on 24 March on site. The facility will be taken back by the operating company on 16 June in preparation for the 40th Hungarian Formula 1 Grand Prix, which will take place on the first weekend in August.
At the event, it was also revealed that the contractors will complete the project elements beyond the scope of the original plan by the June deadline. Thanks to this early completion, several hundred additional seats beyond the original plan will be available for sale for the 2025 Hungarian Grand Prix. These tickets are now available on the top level of the new grandstand, with five additional sectors opening on the Hungaroring Platinum grandstand – as can be read on the Hungaroring social media page.
It was also revealed at Monday's event that there are very few tickets left for this year's race, with organisers expecting a full house.
The roof structure of the main roof is ready, the cladding is already under way
Zsolt Gyulay, CEO of Hungaroring Sport Zrt., said at a press conference at the Mogyorod facility,
The paddock building is in order, the first level, where the paddock club will be, only needs mechanical work and the new 7×21 m boxes are ready to be paved. "The cladding of the building's facade is also underway and the glazing will be completed in time for this year's Formula 1 race weekend"
- said the leader.
In response to a question from our newspaper, Gábor Richter, Technical Director of Hungaroring, said that the early completion is due to the capacity and efforts of the contractor consortium. "The project is being carried out in six working days a week, in stretched shifts, with tremendous momentum, thanks to which, among other things, the second floor of the paddock building will be almost ready."
The roof structure of the main roof is ready, the cladding is already under way
Zsolt Gyulay also said that only two of the 12 tower cranes are now working on the track, but they will be removed this week. He said that the roof structure of the main roof on the finish line is ready, and the upper and lower paving is underway.
Last Friday, we published an impressive video showing the final element of the roof structure being lifted into place last Friday. The construction of the heavy structure, weighing a total of 1,300 tonnes and covering an area of 8,976 square metres, took around four months and was completed in mid-March.
The work on Hungaroring is now a model for other racetracks
The CEO also reported that representatives of Formula One Management (FOM), the race series' management company, visit Mogyoród on average every two months to inspect the facility.
"They look at every detail, and most recently, for example, they brought their Australian colleagues here to show them that you can renovate a track in this way, with this quality. Obviously it's an honour and a very good feeling for us, but at the same time it's taken a lot of work and a lot of difficulty to get to the point where the work on Hungaroring is being used as an example for other tracks," said the sporting director.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure