Here are the latest details on how the M1 six-lane upgrade is being prepared
The investor's MKIF Magyar Koncessziós Infrastruktúra Fejlesztő Zrt. CEO Tamás Németh was the first to inform our newspaper in a comprehensive interview last October, he was the first to inform our newspaper that the M1 motorway would undergo a development of significant importance for national transport.
The project involves resurfacing around 80 km of the M1 from the M0 motorway to the Concó rest area and widening the M1 to 2×3 lanes + ITS (the latter is short for Intelligent Stopping Lane).
The project is already in its preparatory phase, and the implementation of the main elements will begin in September 2025 at the latest. We have reported on the preparatory phase on several occasions, including in protected plant species had already been completed, or during the test piling is underway. We are now writing about the tree felling work based on the MKIF Zrt. Facebook post .
As many trees as are felled, so many will be planted
The M1 motorway widening project will require the felling of trees alongside the motorway. The work requires the felling of thousands of cubic metres of trees, without which the widening of the motorway and the development of transport would not be possible, they say.
However, they stress:
In place of the felled trees, replacement forests of the same area will be planted in the place designated by the state to ensure that the expansion of the motorway does not reduce the country's forest area.
However, the pitch will not be without green space: after the extension, there will be trees, bushes and shrubs closer to the fence, just as before.
Social firewood from harvested wood
State-owned timber extracted during the expansion of the M1 motorway can be requested as social firewood in accordance with the relevant legislation. For a list of eligible organisations and how to apply, see MKIF Facebook post.
Source: Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November