More than two kilometres of ballast cleared on the Budapest-Cegléd railway line

Published

The main member of the SWIETELSKY Vasúttechnika fleet, the RM 80 UHR bedding machine, was working in the section.

Instead of the planned five days, the employees of SWIETELSKY Vasúttechnika Kft. employees completed the ballast replacement tasks between Cegléd and Ceglédbercel in two and a half days instead of the planned five days. The company carried out railway track maintenance on behalf of MÁV FKG Kft. on a section approximately 2,370 vfm long, using the RM 80 UHR ballast cleaning machine.

At the customer's request, the screening was carried out in a width of 4 metres and 30 cm below the level of the concrete substrate - informed our newspaper Gyula Patyi, machine operator.

The purpose of screening is to remove the dirt from the ballast material without disturbing the track structure. The crushed stone screening process consists of screening out the fraction below 32 mm from the dismantled ballast and discharging the crushed stone by conveyor belts to the railway track.

Once cleaned, this fibre is later used to reinforce the floor. However, if the customer so requests, the sorted waste and dirt is sometimes transported away in the MFS truck specially reserved for this purpose," added Gyula Patyi.

At the start of the work, a so-called "tie-in" area was set up, where two or two concrete bases were spread apart, a pit was dug in the bedding, and the machine's scraper chain was inserted into it.

The excavated material is sent to a three-plane screening plant, which removes the coarser contaminants and filters out oversized rock material. Crushed stone that has been screened to specification is re-installed.

The aforementioned cleaning of the bedding is carried out during the screening process, which also creates the right material structure for the bedding. The SWIETELSKY Vasúttechnika staff used the RM 80 UHR bedding fibre machine developed by the Austrian company Plasser & Theurer to carry out the task on the section from Cegléd.