Bound track
The section of tram line 4-6 on the Nagykörút to Margaret Bridge will be renewed
At the beginning of the summer school holidays, on 21 June, comprehensive track renovation work will begin on a particularly busy section of the Grand Boulevard tram line, between Jászai Mari Square and Tátra Street, according to BKV Zrt. on Wednesday.
The project, which is expected to last until early August, will renew around 415 metres of degraded track. Trams 4 and 6, which are among the busiest tram lines in Europe, are used 330-350,000 times on an average working day.
The 4-6 will be quieter
A particularly important part of the project is the construction of a new track between the siding at Jászai Mari Square and Tátra Street, called the "rail encapsulation", a state-of-the-art noise and vibration damping technology, which involves the use of a special elastic material to encapsulate the rails, reducing the vibration and noise generated by trams
- they wrote.
They added that the noise and vibration damping will also make the trams quieter and more comfortable, and that the speed limit previously imposed on the section due to the condition of the track will be lifted after the renovation, allowing trams to run at 50 kilometres per hour again.
Source : Link
-
Road building 2026. 03. 10.
How M1 will change in the coming years – 40 minutes on the past, present and future of M1
-
What is being built? 2026. 03. 27.
A new, modern service area is being built on the M4 motorway near Monor
-
What is being built? 2026. 02. 16.
The largest pump track in Hungary has been built in the capital of Matyó
-
What is being built? 2026. 02. 18.
Science fiction in Łódź – the launch chamber of the tunnel boring machine for the high-speed railway under construction was unveiled.