What is being built?

The LATEREX Építő Zrt. works on three iconic buildings in Esztergom at the same time

Published

The partial renovation of the Franciscan High School and College in Timisoara, the Parish Hall and the reconstruction of the Town Hall are taking place simultaneously.

It is rare for a single contractor to be able to perform tasks that are close to each other and carried out in parallel in one city. LATEREX Építő Zrt. has extensive experience in the construction of modern buildings and the renovation of historic monuments. It is a fortunate coincidence that in Esztergom, it can demonstrate all these competencies in projects that are very close to each other: the partial renovation of the Pelbárt Franciscan Grammar School and College in Temešvár, the partial renovation of the County Hall and the renovation of the Town Hall are all taking place at the same time. Visitors to the LATEREX construction sites in Esztergom need only take a few steps to find themselves surrounded by 18th-century structures after passing through automation-controlled systems. This not only makes their work extremely varied, but also offers plenty of challenges.

 

 

Almost a century of stories - the grammar school

Since the Temesvári Pelbárt Ferences Gimnázium és Kollégium's June topping-out ceremony, the entire roof has been insulated, the extensive and intensive planting media for the green roofs have been installed, the installation of outdoor metal furniture, and the planting of vegetation and installation of the irrigation system are currently underway, according to Péter Koncsek, chief project engineer, who is responsible for the renovation of the grammar school as well as the County Hall and Town Hall. Many details are in the final stages of completion, including

  • the installation of the front windows
  • 85% is in progress for the installation of the facade mounted brick pavers,
  • within weeks, the terraway paving for the inner courtyard will be completed and
  • the outdoor gym park is finished.

 

 

The electrical and mechanical installations in the interior are almost complete, the windows have been installed and the lifts are currently being installed. The cold tiling is fully in place and the installation of the hot tiling, including the sports flooring in the hall, is planned for next year. Details of the interior structures and the educational and sports technology equipment will also be installed next year.

 

Baroque heritage - the Castle House

The contractor is responsible for the construction of new offices on the first floor of an internal wing of the County Hall complex, built in the first half of the 20th century.

In the framework of the project, LATEREX will carry out a complete replacement of the existing stock of windows and doors by remanufacturing the old ones: perfect replicas of the existing ones will be installed under the supervision of the heritage office. In addition, the bathrooms will be renovated and the mechanical system and the low and high voltage networks will be upgraded. In addition, the tiling will be replaced and the finishes will be renewed.

The works, which started in October 2023, will be handed over in February 2024.

In connection with the transformation of the City Hall, the building's wing on Bottyán Street, adjacent to the City Hall, is undergoing a facade and partial interior renovation.

 

 

The oldest in the country - the Town Hall

More serious improvements are needed at the Esztergom City Hall, which has not been renovated for nearly 60 years. The facade and roof structure of the building have deteriorated significantly in recent years.

The special feature of the project is the listed status of the building: the renovation requires the involvement of several restorers and highly experienced contractors, and the aim is nothing less than to restore the original beauty of the Baroque building, which has been a town hall for almost 300 years, in a way that is worthy of its rich heritage.

 

 

The renovation, which will start in October 2023 and is expected to last until spring 2025, will include

  • a complete overhaul of the existing roof structure and, after the necessary reinforcements and structural replacements, the replacement of the entire roofing from the existing asbestos slate to natural slate;
  • renovation of the entire façade, including the existing windows and doors, trim, stonework and finishes.
  • New, grouted insulation is applied to the entire external and internal wall construction,
  • incorporate a panoramic lift,
  • and a new mechanical platform will be created by replacing the slab of the existing courtyard building.

 

 

The internal courtyard of the office will also be completely renewed with the renovation and transformation of the built and natural environment. In addition, the partial internal reconstruction of the Bottyán Street and Széchenyi Square wings will create commercial and office space.

Source : Link

Popular