What is being built?
The Hungaroring's major development is here
The second phase of the renovation of the Formula 1 race track in Mogyoród was presented at a press tour on 12 February. The consortium of Market Építő Zrt. and Bayer Construct Zrt. began work on the new phase last December. As previously reported, in just a few weeks, the two companies' experts moved 20,000 cubic metres of earth and demolished 5,000 cubic metres of concrete, while also erecting the first tower crane.
At the same time, another construction project is underway at Hungaroringen, which we last wrote about in this article last December. rel="noopener">we wrote about in this article last December. As part of this project, the consortium of Fejér B.Á.L. Zrt. and WEST HUNGÁRIA BAU Kft., commissioned by Hungaroring Sport Zrt., is constructing a new, iconic entrance building that will house a café, shop, reception, operations centre and office building.
In the second phase, the ten thousand-seat main grandstand will also be renewed
In the second phase under consideration today, Market Építő and Bayer Construct will demolish the main building and replace it with a cost-effective, modern main building. They will build 4 technical and 36 competition boxes, with a competition control centre, catering and VIP areas attached to the main building, and will also extend and renovate the paddock area. In the second phase, the 10,000-seat main grandstand will be renewed and two pedestrian tunnels will be built.
The work is supported by nine tower cranes
At a press event on Monday, Prime Minister Gergely Gulyás said that the Hungarian state will save 107 billion forints through the royalty reduction negotiated during the extension of the Hungarian Grand Prix contract. Less money than this will be used to complete the full renovation of Hungaroring, which is currently underway and will be completed in 2026. He said that the cheapest bid won the public procurement procedure, worth HUF 78.9 billion and including a 10 per cent margin.
He also said that a total of 9,000 people will be working on Hungaroring during the modernisation, with 57,000 square metres of building being constructed, 125,000 cubic metres of earth being moved, 34,300 metres of reinforced concrete structure being installed and nine tower cranes supporting the work.
He explained that today it is the only other circuit, apart from Monza, to have hosted a Formula 1 Grand Prix without interruption since 1986.
The second phase will be the most critical
Zsolt Gyulay, President and CEO of Hungaoring Sport Zrt., emphasized that the paddock will increase by 3,000 square meters to roughly 8,300 square meters, while the main building will have a floor area of 31,017 square meters, meeting the requirements of the International Automobile Federation. "The biggest test will be between this year and next year's Hungarian Grand Prix, when the main building and the Super Gold grandstand, which is on the home straight, will be demolished and rebuilt," said the CEO.
Zoltán Juhász, technical director of Market Építő, said that 22 kilometres of piles have been placed so far, and 8,000 cubic metres of concrete have been poured. In addition, 65 thousand cubic metres of earth have been moved. "Originally, the plan was to build the retaining walls and do the utility work first, but we thought it was important to tackle several areas at once so that when we had to work on the main building, everything would be ready," he said.
In conclusion, he confirmed that the second phase will be the most critical, as it will involve removing a complete 280-metre-long building and rebuilding the foundations in ten and a half months so that the pits can be used as intended for the 2025 Grand Prix.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure