730 tonnes of giant equipment arrived on the Danube for the construction of Paks II

Published

One of the most important safety components of the power plant arrived in our country by water - the Danube.

The Paks expansion has reached another milestone with the arrival in Hungary of one of the most important long-lead items of equipment, the zone melt trap, which was transported by water from Russia, announced Péter Szijjártó, Minister of Foreign Affairs and Trade, on 1 August.

As the ministry's statement underlines:

Now Paks is the largest nuclear project in Europe, and all such construction projects have certain milestones, such as the arrival of long lead times for equipment.

The minister pointed out that the newly arrived meltdown trap is an important safety device for the nuclear power plant, located directly below the reactor vessel, which can catch any liquid spilling out of it in an emergency. This is a huge device with a maximum diameter of 11 metres, a height of more than 15 metres and a weight of over 730 tonnes, about which we published a detailed article in our newspaper shortly after it was completed in St. Petersburg.-5-blokk-elso-nagyberendezese" target="_blank" rel="noopener">published a detailed article about it shortly after it was completed in Saint Petersburg.

 

The mass of 15 modern airliners

He then illustrated the dimensions of the structure with a plastic analogy. "If you want to compare it with something that is used in everyday life, it is equivalent to the weight of about fifteen A320 Airbus aircraft in total", he said.

The production process was continuously monitored by Hungarian experts and the National Atomic Energy Office to ensure that the safest and best possible device was produced.

 

Paks II Zrt.

 

42 days on the water for the zone trap

The delivery took place on 29 March, but not only the production, but also the delivery took a long time. "Typically, an international project requires international transport. The transport was organised by an Austrian company, and the booby trap arrives in Paks on a Slovakian boat after a total of 3,200 kilometres of water transport, which took 42 days, and the booby trap and its equipment had to be loaded several times across the Black Sea and the Danube", he said.

 

Paks II Zrt.

 

Nine hundred people are already working at the Paks II construction site

The minister said that the Paks project site currently employs 900 people, and that at peak times the workforce will be between eight and ten thousand.

He also pointed out that

Over 21,000 of the 76,000 piles needed for soil stabilisation have already been drilled, and the soil stabilisation under the future nuclear island of Unit 5 is already 86% complete. This, he said, has paved the way for the full excavation operation to a depth of 23 metres to begin.

"The zone meltdown trap, which is one of the most important elements of the safety of a nuclear power plant, has therefore arrived at Paks. Our experts are now taking over the zone melt trap, and construction work is in full swing so that the new units of the Paks nuclear power plant can be ready for operation from the beginning of the next decade", added Péter Szíjjjártó, among others.

Source : Link