World-class Hungaroring introduced
Over the past two years, we have reported on numerous occasions about the historic transformation of Hungary's only Formula 1 race track. By 2026, the main building and grandstand will be completely renovated by the developer Market Építő Zrt. and <a href="https://www.facebook.com/Market Építő Zrt.?fref=toget rel="noopener">Market Építő Zrt. and Bayer Construct Zrt..
The new main building and main stand of the Mogyorod circuit were unveiled to the press for the first time, and journalists were able to see for the first time what the Hungaroring will look like at the 40th anniversary Hungarian Grand Prix.
A Red Bull F1 car was appropriately „parked” on the newly resurfaced finish line. It arrived in Hungary to promote the Red Bull Show Run in September, which Hungaroring is joining as a sports partner, according to the Hungaroring's announcement. This time, the car's role was to show what a spectacular sight awaits the drivers when the entire F1 field lines up on the starting grid between the brand-new main building and grandstand on the first weekend of August.
A real country image
At Thursday's press conference, dr. Ádám Schmidt, Minister of State for Sport at the Ministry of Defence, said:
"I think that the Hungaroring deserves a new, modern look for its 40th birthday, as we can say without exaggeration that the track and the Hungarian Grand Prix are a significant part of the history of our country. It arrived on the eve of the change of regime and over the decades it has become one of the favourite venues of the Circus of Solitude.
As he pointed out, "the Hungarian Grand Prix is usually our most visited domestic sporting event, last year more than 300,000 people attended the event, and the total GDP generated by the event exceeds HUF 26 billion."
Zsolt Gyulay, CEO of Hungaroring Sport Zrt., presented the new main building and main stand, and said that, as in the past three years, they expect a full house at the race weekend.
"This is not just an infrastructure development, but the beginning of a new era for Hungarian motorsport. Every element of the new main building and grandstand is designed to provide a world-class experience for drivers, teams and fans alike."
Although the work will not be completed until next year, you can already see what a beautiful and internationally renowned course is taking shape.
"A huge thank you goes to the Hungaroring team, the development team, the contractor consortium and everyone who contributed to this transformation," he said.
"I returned yesterday", he added, "from the premiere of the new Formula 1 cinema, and besides the same amazing interest that we see on race weekends, I must say I was very proud to see that Hungaroring was highlighted among the tracks in the film, with the name of our capital, Budapest, mentioned several times - in a positive context. In my opinion, few things can do more to build the image of a country".
We are among the best
The paddock area was already enlarged for the last Hungarian Grand Prix, and since then the main building (although not yet fully occupied by F1 this year), the main grandstand and the event area behind the main grandstand have been renewed. As Zsolt Gyulay pointed out:
"In order to speed up construction and to ensure that the Hungarian Grand Prix could be on the calendar during the renovation, it was important that the building's structure was made of prefabricated elements."
The new main building has 36 competition boxes and 4 technical boxes; a VIP area on the first floor with a capacity of 2,000 people on the pit lane side, with boxes; and a restaurant with a kitchen and seating for 80 people.
A new 13,000 square metre covered main terrace has been built, which includes a VIP terrace in addition to the commentator's gallery. The new main building and the main arena will be connected by a tunnel at the beginning and end of the finish line, to provide access for the organisers, athletes and visitors.
The most interesting construction figures since last year's Hungarian Grand Prix
Total net building area: 42 694 m2
Main building (net floor area: 19 753 m2)
- 54.000 m3 earthwork
- 9,128 km, 508 tonnes of iron for piling
- 33 476 m3 concrete, 2.418 tonnes of reinforcing steel
- 10 lifts
- 11.699 m2- design of a fire alarm system
- 293 interior and fire doors
- 5.516 m2 resin covering in the boxes
- 465 paddock club vip-view chairs
- 425 m2 office on first floor
Main terrace (net area: 13 133 m2)
- 10 296 seats with covered grandstand,
- 9600 m2, 1125 tonnes of steel roof structure
Event space
- 16 577 m2 construction of an event area and retaining wall
- 3.903 m2 TV COMPOUND
Building in depth
- 2 tunnels
- 6832 metres of sewer (sewer and stormwater)
- 2345 metres of water pipes
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure