The massive beams had to be lifted out of position one by one using a crane with a lifting capacity of 650 tonnes.
The demolition work carried out on 10 March posed significant challenges in terms of both logistics and traffic management at the mega-interchange currently under construction on the M44 motorway near Kecskemét.
A temporary traffic closure will be required on the right lane of the M5 motorway in order to remove the beams of the bridge to be demolished. The status of the project being carried out by Duna Group will also be...
Its expertise, innovative solutions and reliability have made the SWIETELSKY Magyarország Kft. an indispensable player in road construction. The company is also a leader in asphalt production, recognising that this will bring even greater...
Careful preparation enabled them to halve the duration of closures during beam lifting on the motorway development project in the Kecskemét area. The Hódút Építő Kft. project is the largest in the country...
The girders of the M44 motorway bridge over the M5 motorway will be lifted next week; temporary traffic closures on all three roads concerned are expected in the evening hours from Tuesday to Sunday.
Contractors in the Kecskemét area face an unusual challenge, where the M5 motorway, the M44 motorway, which continues into the M8, and the 5 main road intersect at a triple junction. The Hódút...
A total of seven new structures will be built at one of the largest national interchanges in the country, with ÉKM investing in the construction of the Hódút Építő generic construction.
The 32.3 km section of the Hódút was the final stage of a comprehensive series of investments.
They announced the renovation of the Kecskemét-Dabas-Budapest railway line, the four-lane upgrading of the main road 5 to the Mercedes factory and the modernisation of the Halasi road overpass, among others.