Road building
Important milestones reached for the western section of the M44
Construction of the western section of the M44 expressway connecting the M5 motorway with Békéscsaba is progressing at a good pace. The 32.2-kilometre four-lane road between the motorway and Szentkirály, which is being built on a new route, is being constructed by Hódút Építő Kft.
Significant progress on the load-bearing paving slab
According to our newspaper, the progress of the Építési és Közlekedési Minisztérium (ÉKM) project has also been helped by the favourable weather. Since our last report
The earthworks for the road construction were roughly completed in 85%
- And if there are no more severe frosts, they will continue working until the beginning of December. An important milestone is that the cement-bonded load-bearing pavement is now half the length of the section, with a layer of asphalt covering the right and left sides. The construction of the pavement base is currently underway on the new section of the 441, which will be covered by a base layer of asphalt this year. (The section between the two roundabouts dividing the M44 slip roads on the 441 between Nagykörös and Kecskemét, which is being renewed by Colas Zrt., is being built by Hódút Építő)
Underground water works (construction of longitudinal and cross drains) are almost complete, as are the utility replacements; trench paving should start in spring 2024. The kerbstones and paving of the simple rest area on the left have been put in place, and earthworks are currently underway for the rest area on the right, while the protective ducting for the plant communications cable is being constructed along the entire section.
Preparing for winter
The contractor is preparing for the winter shutdown in good time: the construction of depots to store the spreading materials from January is underway. The finished paving slabs will be covered with a base layer of asphalt, which will also provide temporary drainage to ensure that any winter precipitation does not wash away the finished pavement surfaces. In some places on the main line, the cross-traffic of the public will still have to be managed while work is ongoing. To this end, barriers will be built before winter to prevent access to the work area or to the completed works.
The beams were lifted in three nights
On the final section of the motorway, 14 structures are under construction, of which the roadbed is already in place on eight bridges and the beams are in place on all of them.
One of these is the bridge over the Budapest-Szeged railway line.
Due to the construction of the Budapest-Belgrade railway line, the Szeged line was significantly congested, so it was only possible to close it for a minimum period.
They asked for a date in the summer of 2022 for a period without trains when the beams could be installed, which was granted for the summer of 2023. A very strict schedule was set for the construction of the structure, and as a result the bridge deck beams were successfully lifted in the three (!) nights allowed. Construction of the bridge could then continue without interruption, with the deck slab expected to be completed in November this year.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about