What is being built?

Professional prefabrication on Bayer Construct designs

Published

We present the VIASTEIN prefabrication plant in Biharkeresztes, part of the Bayer Construct group, and the journey of the concrete elements to the ZVK project under development in Zugló.

With more than 20 years of professional experience, the Hungarian-owned Bayer Construct is one of Central Europe's leading construction and property development groups. Prefabrication is becoming increasingly common in the buildings they construct, as one of the company's main strengths is efficiency, both in terms of costs and human resources. The company purchases the prefabricated elements required for its buildings from VIASTEIN Kft.. VIASTEIN Kft. It began production at the paving stone factory in Biharkeresztes in the second half of 2017, and in 2018, a paving stone refining plant was completed at the same location. Prefabrication of concrete elements began in the summer of 2021 as the third phase of development of the factory complex at the state-of-the-art plant.

The production of preassembled products is a major driver of efficiency, which is a priority for the Group. They help to reduce construction costs and construction time in certain construction developments and projects.

The plant, which is rare even in Europe due to its extremely high level of equipment and high precision concrete product manufacturing capabilities, will produce a variety of elements for the Zugló ZVK project investment. Eight buildings – one residential and seven office buildings – are being constructed on a seven-hectare site next to Bosnyák Square.

In this article, we describe the manufacturing process and the strict schedule for their installation in the facilities under construction for the ZVK project in Zugló.

Prefabrication has many advantages

Prefabricated elements require more preparation, but require less time to install on site. Structures are more dimensionally accurate, have more consistent quality and the positioning of the installed materials is more secure. As a result, the construction is more cost-effective and faster," says Gergely Szalai, project manager of the ZVK project.

Two types of prefabricated elements are used in the ZVK buildings:

  • on the cellar floors bark panels - these are 5-7cm thick plates, which incorporate the bottom mesh reinforcement, the tirgons and if necessary cooling-heating piping, as well as mechanical, electrical boxing and exclusion. They are then overlaid with a layer of concrete to shoulder the load-bearing capacity.
  • And at the ascending levels circular hollow planks which are thicker and therefore do not require temporary support during construction. No mechanical or electrical components can be integrated into the circular planks.

In the project in zugló, the most modern bark panel elements manufactured in Biharkeresztes so far were installed, for example, in the Zenit Residence and the Office1 and Office3 office buildings.

Product design is the foundation of everything

We asked Zsolt Kovács, Managing Director of VIASTEIN Kft., about the preparation and production process of the concrete elements.

When asked, he explained that the production of building components is based on product design, which is carried out by the experts in the design division of Bayer Construct Zrt.. The preparation of the ZVK project in zugló started already in 2021.

The aim was standardisation, i.e. to design uniform elements with slight geometric variations that are most efficient to produce, as they can be produced more quickly and easily from templates.

Earlier, Tamás Iski, head of the design division, told our newspaper that they do not simply provide a product design, but also an information package to the plant: quantitative and geometric data that help to track changes in inventory, as well as data for the automated production lines.

"The designer has a great deal of freedom in terms of bark elements, because on the production line we work with any geometry between minimum and maximum dimensions. From a transport point of view, and because of the manoeuvrability and crane handling, we produce elements up to 2.4 metres wide and 8-9 metres long", the director began.

Production of the bark panel element

A total of 40 3×12 metre tables will be used on the Progress production line, with production starting with an automatic shuttering robot. The elements are not produced in a single template, as is the case with columns or beams, but are individually formed, each element being re-shuttered by the robot. After the formwork has been cleaned, the robot uses the production data to form the geometry and records the position of the technical units and wiring on the table.

Then the electrical boxes are placed on the table with their magnetic connection points, and at the next station, the pre-ordered cooling and heating panels, electrical junction boxes, switches and light wiring are inserted under the reinforcing steel mesh in the positions painted on the plans.

"It is not uncommon for a single bark panel to extend into several rooms, so it is not uncommon to find the location of individual ducts, outlets and cooling-heating panels. This is why product design is of paramount importance", Zsolt Kovács underlines.

Earlier in our article on the Bayer Construct BIM-based design, Tamás Iski, head of the design business, also talked about the importance of coordination and non-collision of different disciplines. In the case of concrete panels, the individual mechanical units must be designed and installed with millimetre precision so that, once the panel is installed, they fit exactly into the mechanical and electrical units of the building structure.

After installation, the steel mesh (produced by an automatic mesh welding machine on the production line), the trigonal bars that give stability to this 5-7 cm thick bark, are placed on the element, which after concreting is placed in the maturing chamber, where it is removed after 8 hours and the next day or the same day, depending on the production schedule.

"The bark gel production line has a huge capacity. It can run up to three shifts. In one shift - that is 8 hours - it produces 1,000 square metres of elements, so it can meet the needs of several projects at the same time" - explains the plant manager.

The hollow pallet is produced on an Italian production line

Also for the ZVK project buildings - but not only there - the plant in Biharkeresztes produces large quantities of hollow planks. These are much thicker structures than the bark panel elements, 20-25 or 30 cm thick, 120 cm wide and with limited geometry.

"Hollow planks are widely used in industrial halls and office buildings. Because they consist only of concrete and the prestressing paste inside, they are more delicate structures than bark and have more limited penetration. At the same time, they are highly efficient, low cost and do not need to be supported during construction. Hollow planks have a high load-bearing capacity, up to 50 cm thick, which can be used in car parks or larger structures"- explains Zsolt Kovács.

They are produced using a range from an Italian manufacturer, Nordimpianti, together with all the equipment in their range. On the production line, after concreting the 120 m bench, the automatic cutting machine cuts the elements at the angle and where they are needed, according to the specifications given in the production drawings. If necessary, the Biharkeresztes plant can even pre-drill slab cross-cuts (which is more practical) or drill them afterwards.

"The technological interest of the production is that the hollow block is made of concrete with earth moisture, as shown in the video. Its stability is so high that it can be placed on the element practically immediately without it sinking or collapsing. Like the bark panel element, it is usually removed from the bench or cut up after 8-12 hours. Here too, production is continuous, on several benches."

Tight scheduling and delivery

The finished concrete elements are delivered to the construction site in Zugló according to a precise schedule. Six of the project's eight buildings are currently under construction at the same time, at different rates. In our previous article, we presented in detail the precise organisation of the ZVK construction project.

Project manager Gergely Szalai explained that they plan the work processes, the supply of tools and materials two weeks in advance, almost to the hour. Accordingly, there is continuous coordinated communication with the VIASTEIN plant in Biharkeresztes. The production of prefabricated elements is coordinated in advance according to a strict daily schedule.

As Zsolt Kovács, managing director of VIASTEIN Kft. pointed out, they need to know about 1-2 months in advance: which elements are needed, by what deadline, and how much. This is also important to be able to order the materials and tools needed for production and to have them available for production.

But not only the production, the delivery is also carried out according to a precise schedule, as it is not possible to deposit large quantities of finished elements on the project site. In addition, it is practical and efficient not to have to unload the concrete elements from the semi-trailer, but to have the crane lift them immediately into the building structure. The cranes and other equipment must therefore be exactly in position at the right moment. With a tight schedule, there are no delays, no buffer times.

When installing the individual elements, particular attention must be paid to the positioning, otherwise it only takes 5-7 minutes to install one element. The installations are practically continuous since, as mentioned above, several buildings are being constructed in parallel on the site.

"We have been working with ZVK's project managers and construction managers for a long time. We communicate constantly, if there is a change, we deal with it immediately and reorganise. It's that simple", adds Zsolt Kovács.

For the delivery of large-size products from VIASTEIN Kft. Mercedes-Benz vehicles with extra parameters are used for the delivery of large-size products. In 2021, the company purchased eight new tractors and special trailers.

Green Code - for efficiency

As a member of the Bayer Construct group, the VIASTEIN Kft. strives to achieve the most efficient operation possible. To this end, in addition to the machines that are part of the production line, the Progress Group's ERP system has been purchased, which covers the entire workflow from quotation to invoicing, and even includes the control modules for each production line.

The company has also acquired the Green Code licence, which is in fact Progress' knowledge base, developed specifically for property developers, manufacturers of precast concrete elements. It provides international experience not only in design, but also in production, transportation, storage and site issues.

Source : Link

Popular