What is being built?

Prefabrication can radically reduce not only construction time, but also design time

Published

With a clever solution, Zugló's most important investment Bayer Construct Zrt. will be built in just two building types

By putting its prefabrication plant into operation, it plans and builds the supporting structures of the Zugló ZVK project more efficiently than ever before. Bayer Construct Zrt. We discussed the details with Tamás Iski, head of the design division, who emphasised from the outset that a precisely designed building structure is of utmost importance.

For each building, the general designer defines the form and function of the building, and it is up to the sectional designers to supplement this and move towards more detail. As a sub-task, Bayer Construct also understands structural design as the preparation of the structural design, but the work is different in detail: the company has its own structural division to ensure that its technologies are applied and that the construction process is as smooth as possible.

The BIM method is used in the production of plans, the scale of which has necessitated the creation of a separate department responsible for coordinating models and filling them with information. (Our newspaper has previously reported in detail on the design business and the application of BIM.) They consider BIM coordination to be mandatory for themselves and their subcontractors, as it makes the management of complex tasks as efficient as possible.

 

Construction of the ZVK project in zugló

 

A separate set of criteria has been built

For Bayer Construct, a primary concern is that the work that is carried out on site is supported by structural design in a timely manner. The structural design is completed with sufficient certainty before construction, as this ensures the continued operation of the group. It is of paramount importance to the company that plans are never delayed.

Although the basic considerations are similar to those of other companies: to be fast, cost-effective and do a good job, the Bayer Construct staff are trying to achieve all three at the same time, which requires a new approach. The designers are also tasked with producing structural designs - in collaboration with the general designer - that make the best use of the company's construction technologies and the products of the manufacturers of interest.

Among these, the reinforced concrete prefabrication plant in Biharkeresztes is the most important, because the products manufactured there enable faster and more accurate construction, with virtually no waste and less labour. We recently made a spectacular video about the plant spectacular video about the plant, and we presented the manufacturing process in detail, as well as the importance of prefabricated elements in projects.

 

 

Coordinated workflows

It is usually a basic expectation for designers to have all plans ready before construction starts. Typically, the developer commissions the plans and then puts them out to tender, so that he can hand over ready-made materials to the winner. This ideal situation is often not realised in Hungary because the timeframe for each task is so short that they are merged, so that the design is carried out in parallel with the construction.

Taking advantage of this necessity, Bayer Construct has rethought the design and construction arrangements for the ZVK project in Zugló, for which the company is the investor, designer and contractor, so that - in-house - there is no conflict of coordination.

"Here we schedule so that the plans are ready a good month before they are needed, so there is continuous, parallel work," Tamás Iski told us.

It is also special because the structural design is followed by the production design phase, i.e. the plans are first sent to the production plants: the reinforcing steel processing plant has to produce the necessary raw materials and the prefabrication plant has to prepare the elements to be installed.

 

 

Although the construction is not yet at the stage where the design can be finalised, all the final designs may be available to the contractors this year - so the documents will be issued earlier than usual. This is because very few monolithic structures have been used for the buildings.

Building the facilities for the ZVK is a huge task in terms of scale. Seven of the eight buildings are currently under construction at the same time, and one has already been completed. Construction work has started in stages and the structural design is being prepared at the same pace as the construction.

 

You can already see the results

As Tamás Iski points out: from a design point of view, the advantage of prefabrication was most visible at the end of the process: at the beginning of the work, careful design required a lot of capacity and time, because many elements were developed for all the buildings. As the head of the design business pointed out:

"Many of the elements were designed with the fact that they will be needed in many buildings in the future in mind."

As they progressed with the processing of the buildings, the tasks became faster and easier, because there was a proliferation of structures that had already been designed and just needed to be adapted to the current building.

4,082 reinforced concrete pillars will be used in the ZVK project buildings, for which 340 different element designs were made, and only 130 different types were needed for 3,286 slab beams. For the slab beams, two types will be used: the now classic bark slab, which is a semi-monolithic solution and always unique; and a circular slab panel, of which 15950 will be installed, and of which a total of 311 semi-monoliths will be needed.

 

 

This way, quantifying it really shows that it is definitely worthwhile to engage in prefabrication and perhaps also shows how many elements need to be designed to be able to work with large quantities in the factories. In addition, the finished product is also a good service for the installation, as the 1,000th slab is already being fitted into place by their colleagues with great routine, which results in more precise work than if each element had to be shuttered, reinforced, concreted, stripped and finally the rubbish produced on the construction site had to be collected separately.

 

Adapting to needs

At the outset of the development, it was a priority to minimise the variety of the buildings' form from a structural point of view. A frame can be dressed up in many ways, but changing the structure is time-consuming and expensive.

 

 

Of course, the residential and mixed-use office buildings are slightly different, but the two building forms are very similar, so they were able to incorporate elements here too. Basically, all the buildings have the same floor plan and only in the number of levels were the designers allowed to vary where necessary. Buildings 2, 3 and 4 are almost identical: three levels of underground parking, ground floor and eight storeys; buildings 5 and 6 have one level of underground parking and seven storeys. Unfortunately, Building 7 could not be included in this scheme because of its specific function.

"The result of this solution was that we had two basic types of support structure instead of seven, which greatly facilitated the design work," summarized Tamás Iski.

 

Implementation can be even faster

The ZVK's underground garages cover the entire site area and had to be designed as individual structures, but this may change in the near future as experience is gained. They have a number of technological and design ideas that will be introduced in future construction projects and will allow even more prefabricated elements to be incorporated into the houses. A new trend is the use of prefabricated reinforced concrete for reinforcing cores and waterproofing basement walls, which will be used in the next Bayer Construct projects, making construction even more efficient.

 

Source : Link