What is being built?

The port of Mohács takes shape - This is how the retaining wall system of the dock in the Danube riverbed is built

Published

The construction of the public port in Mohács by PLATINA-BAU Zrt. has reached a spectacular stage. The more than 5 m high reinforced concrete retaining wall and other reinforced concrete structures of the dock are being built by CLC-Construct Kft. with formwork and working platform systems by MEVA. The works are challenging not only because of the complexity of the project, but also because of the Danube flooding.

In September 2021, the foundation stone of the public transport port was laid in Mohács, which will be an intermodal hub able to receive cargoes arriving by road, rail and water. The development includes the construction of more than 300 metres of seawall, as well as roads and railways. In addition, two berths for loading and unloading ships will be created, and an open-air storage area will be built on the 2.5 hectare port site.

 

 

The project is extremely complex, and in addition to protecting and relocating existing infrastructure, it also needs to be expanded. In addition, 19,000 square metres of loading area will be paved with concrete, and the connecting road network and service roads will be paved with almost 3,600 square metres of asphalt. In addition to the roads, rail tracks and a crane track will be built to facilitate the operation of the new port.

Around 1800 cubic metres of vertical and horizontal reinforced concrete structures are built

 

 

During the construction of the seawall, including the excavation of the embankment, nearly 14,000 cubic metres of earth had to be excavated and more than 60,000 m3 of fill material had to be installed. On the banks and in the Danube riverbed, the work area was delimited by breaking down about 14,000 square metres of reed wall in several phases. The CLC-Construct Kft. specialists will construct almost 2,400 cubic metres of reinforced concrete for the embankment, of which the vertical reinforced concrete structure will be 1,400 cubic metres and the horizontal 1,000 cubic metres.

The retaining and cross walls are simultaneously formworked using MEVA technology

 

 

Csongor Gyulai, chief engineer of CLC-Construct Kft., told us that their tasks include the construction of the 350 m long and 5.2 m high retaining wall system of the port. The chief engineer added that since the retaining wall has to be formed and concreted at the same time as the cross walls, the MEVA technology was chosen for the construction. The two companies' specialists are coordinating the work in close cooperation.

Mammoth at work

Gábor Kecskeméti, sales engineer of MEVA, is the contact person for the implementation. He told our portal that the 300 metres of the new section of the harbour offer many challenges, both for the formwork contractors and the designers.

 

 

Among these, he highlighted the formwork anchoring consisting of 6 dilatations - and within this, 7-9 additional strokes per unit - and the precise positioning of the mooring bucks and anchorage fittings to be placed. These operations were preceded by lengthy planning and consultation. For the reinforced concrete structure of the retaining wall, the 5.2 m high concrete pressure and the on-site installation of the assembly were supported by a Mammut formwork system with Meva Alkus formwork shell. The Alkus formwork shell does not absorb water and retains its size.

The Mammut formwork system is mainly used in industrial installations, mainly due to its excellent high fresh concrete pressure absorption capacity, allowing fast concreting up to high heights. It is also the solution that has saved the most time and labour on the harbour retaining wall.

Scaffolding over the flooding Danube

 

 

The engineer of MEVA added that for the works on the Danube side, the KAB suspended work platform was recommended, which provides perfect safety for the construction workers. The system's prefabricated folding brackets and fold-out railings do not require on-site assembly. When the crane lifts the scaffold, it opens and locks automatically, saving considerable time.

Gábor Kecskeméti emphasized that the cooperation between the two companies is exemplary in dealing with the obstacles encountered during the work, including the flooding of the Danube, which results in a high-quality construction.

For a while the river took over the work area

Csongor Gyulai, chief engineer of CLC-Construct Kft., also highlighted the close cooperation between the two companies. Each square metre of formwork had to be designed separately when the retaining wall was built. This resulted in constant, daily coordination between MEVA and CLC Construct Kft.. The specialists from both companies have worked together for a long time and on many large projects, so the pre-planning of the formwork progressed smoothly. The list of challenges for the works on the waterfront and over the river is extended by the high precision of the crane beam, which is also suited to the Meva system," says Csongor Gyulai.

 

 

In addition to well-functioning formwork systems, the chief engineer added, reliable concrete technology and high-quality formwork release agent are also required for successful construction. Csongor Gyulai said that the seemingly simple structure is complicated by the weight, size and number of structures to be installed. Precise design and construction is required for the port and built-in trestles, steel slipways, crane parts and water transfer and drainage.

The chief engineer added that another challenge is that the retaining wall system requires the tracking of the spike system protruding from the already constructed diaphragm wall, which makes construction difficult and requires continuous fine-tuning of the reinforcement and formwork.

 

 

The fact that they were able to create a well-functioning working level on the upstream side with the KAB brackets is a great help in the construction, added Csongor Gyulai.

The chief engineer said that the project is complex and a great professional challenge, but the biggest test for them is not the construction, but the Danube and its flooding. During the flood risk, work is suspended. Csongor Gyulai noted that the river had shown its strength and for a time completely flooded the work area. But, like the challenges faced during the project, this was managed in time.