What is being built?
Spectacular technology to replace the rails of the Pentele Bridge over the Danube
On several occasions, we have reported on the 1,682-metre-long Pentele Bridge crossing the Danube at Dunaújváros modernisation of the Pentele Bridge crossing the Danube at Dunaújváros. According to a previous report by MKIF Magyar Koncessziós Infrastruktúra Fejlesztő Zrt., the operator and contractor
The structure, which was inaugurated in 2007, last had its mud replaced 13 years ago. In the meantime, during regular inspections of the bridge, the experts have detected a failure in the dilatations that slightly disturbed the safety of traffic, but did not endanger it. For some structural elements, anomalies were found which adversely affect the expected lifetime of the existing spans. Therefore, this year, the replacement of several spans and the dilatation structure on the approximately 10,400-tonne Pentele Bridge was necessary.
MKIF recently posted a spectacular video, but in mid-May, a member of our staff had the opportunity to take footage of the work in progress during the full closure.
Precisely planned lifting, centimetre by centimetre
In the process, the floodplain bridge was raised 1-2 cm to replace the mud under water insurance
- summarised by MKIF.
Then, going into more detail, they said that it is not really the structure of the bridge piers that is being raised, but the superstructure of the bridge, the part that carries vehicle traffic. Between the pillar and the superstructure is the hinge, which ensures the transfer of loads and the dissipation of movements (e.g. thermal expansion) and allows movements to be tracked in a controlled manner.
To replace the hinges, the superstructure is lifted by hydraulic jacks (so-called presses). This is a pre-planned process: the design of the bridge must take into account that the spans may need to be replaced over time, so the lifting points in the bridge structure are designed accordingly," they added.
The works were carried out under water insurance
The Pentele Bridge consists of three major units: the right bank bridge; the medieval bridge and the left bank bridge. At the road bridge, where the piers are in the water, water insurance will be required during the works. This is mainly for work safety purposes, and a motorboat patrol will be provided on site for rapid rescue.
Two different bridges - two different technical approaches
In autumn 2024, MKIF completed the replacement of the girders on the Kőröshegy Valley Bridge. By way of comparison, individual bridge elements were replaced there, while at the Pentele Bridge, a complete replacement of the bridge elements took place, with the installation of more modern structures.
For the Pentele bridge, because of the different type of spindles, the existing reinforced concrete spindles were cut back with a diamond wire cutter and a steel cap was placed on top of them, on which the new spherical glass spindles were then placed. These are solutions that meet the latest standards and load-bearing requirements.
At the Pentele bridge, the increase in freight traffic also justified the installation of more advanced trusses. When the bridge was built, pot trusses were still used, as the modern spherical glass trusses available today were not available.
Preparing for increasing workload
According to the company, the load will increase significantly in the near future, as the M8 will be joined by the M200 motorway, which is expected to bring more traffic to the Pentele bridge. As well as having a higher load capacity, the new spans are expected to have a longer lifespan.
The two bridges - the Pentele Danube Bridge and the Kőröshegy Valley Bridge - differ in their construction and use of materials:
- The Pentele Bridge is a steel, three-part structure with a basket-arched deck bridge.
- The Kőröshegy viaduct is built of reinforced concrete, with a continuous superstructure along its entire length.
These differences mean that the heels are subjected to different types of load, so it is not possible to compare their wear rates clearly, they explained.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure