From Saturday afternoon, the southern bridge of the Flórián Square overpass will be open to traffic.

Published

Photos: BKK/Simon Nyirő
The structures at the transport hub in District III of the capital are being renovated by KM Építő, with HE-DO also participating in the work.

Approximately eight months after its closure on 1 March, the renovated southern bridge of the Flórián Square overpass will open to passenger and other motor vehicle traffic on Saturday afternoon, 15 November. The overpass in question has received the official permit required for temporary traffic. According to the temporary traffic plan, traffic will be able to travel on one lane for a short section, then on two lanes towards Árpád Bridge and Pest, according to a statement sent to our newspaper by BKK .

This is how preparations are being made for the reopening of the bridge

Even before the opening of the southern bridge, on 14 November, at 8 p.m. on Friday evening, they will begin setting up the temporary traffic system required for the second phase of the renovation – the renovation of the northern bridge. This includes modifying the routes leading to the bridge and the existing traffic pattern under the bridge, as well as establishing a new bus lane on the Árpád Bridge towards Buda. The works will involve temporary lane narrowing, minor traffic restrictions outside peak hours and occasional closures.

The general construction of the Flórián Square project is being carried out by KM Építő Kft. with the participation of HE-DO, as we regularly report. The implementation plans were prepared by FŐMTERV Mérnöki Tervező Zrt..

This is how the temporary traffic arrangements will look in the coming period

An important change is that from Friday evening, the ramp from the northern bridge towards Pest from Szentendre will be closed, while one lane from the Árpád Bridge towards Szentendre will remain open. Until the southern bridge opens on Saturday afternoon, traffic from Szentendre towards Pest will only be possible via the Pacsirtamező Street turning circle.

During the first phase of the transition period between the opening of the southern bridge and the closure of the northern bridge, the following traffic arrangements will be in place at Flórián Square:

  • The renovated southern bridge can be accessed from Szentendre towards Pest via a single lane, which widens into two lanes further on (this traffic arrangement will remain in place for the duration of the complete renovation of the northern bridge), and the exit ramp towards Árpád fejedelem útja will also be open.;
  • Those arriving from Árpád Bridge can proceed towards Szentendre on one lane on the northern bridge, or they can turn right in a slight curve on one lane on Tavasz Street, or they can continue straight ahead on two lanes towards Vörösvári Road.;
  • When approaching from Vörösvári Road, it is still not possible to turn left, but by turning right and using the turning circle on Pacsirtamező Street, it is possible to reach Szentendrei Road.;
  • From Szentendre, below the renovated southern flyover, you can drive straight ahead in one lane towards the Pacsirtamező utca turning circle, with the outer lane remaining designated as a bus lane.

With the gradual transformation of the junction under the bridge during the transition period

  • the lane restrictions will be lifted and Tavasz Street will be widened;
  • Towards Szentendre, you will be able to turn right on two lanes, and motorists will also be able to continue straight ahead on two lanes towards Vörösvári út.
  • Those arriving from Árpád Bridge can proceed in three lanes towards Pacsirtamező Street.

The complete closure of the northern bridge to traffic and its renovation is scheduled to begin on the evening of 21 November. On the northern bridge, as on the southern overpass, the renovation will begin with the removal of the road surface and a thorough inspection of the track slab. Detailed information on the related traffic changes will be provided in a later announcement by BKK.