FŐMTERV has solved unusual tasks for the design of the 83 motorway
Our newspaper has been continuously reporting on the construction of the most important 2×2 lane road in Transdanubia, the new section of main road 83, which is being built by FŐMTERV Zrt. and https://www.tivorimarketing.hu/index.php/a/FŐMTERV Zrt./rel="noopener">https://www.tivorimarketing.hu/index.php/a/FŐMTERV Zrt./rel="noopener">https://www.tivorimarketing.hu/index. rel="noopener">FŐMTERV Zrt. and UNITEF ’83 Zrt. consortium, led by FŐMTERV.
The track between Pápa and Győr was built in two sections, with a total length of 37 kilometres, on behalf of Építési és Közlekedési Minisztérium:
- Between Pápa and Tét (18,4 km) on the Duna Aszfalt Zrt. was the general contractor, here the EuroAszfalt Kft. is a subcontractor (as part of this section, a slip road to the Pápa airport has been built at the end of the track);
- Between Tét and Győr (17,6 km) on the Soltút Kft. the project was carried out under the general construction of the Colas-csoport was also a subcontractor.
Motorists will soon be able to use the new 2×2 lane motorway at speeds of up to 110 km/h: we recently reported that the technical handover is already underway, and now, with the help of FŐMTERV chief engineer Gábor Hevesi, we have learned how the plans for this road, which is of paramount importance to the people of Transdanubia and local industry, were drawn up.
Fewer accidents on the new motorway
The first topic was the changing needs of customers: the preparation of the project dates back to the early 2000s. Gábor Hevesi said: at that time, the organisations preparing the design were thinking about the reconstruction of the 11.5-tonne main road and the construction of municipal bypasses. However, the designation of the military airport in Pápa as a NATO base airport placed new demands on the main road, as the Hungarian state undertook to upgrade its road connection to 2×2 lanes.
In addition, the technical parameters of the original Highway 83 did not meet the requirements of the call for tenders:
- The old route passes through the interior of each of the municipalities concerned, so the environmental impact of traffic is detrimental to the quality of life of the inhabitants.
- There are several accident black spots on the Tét-Győr stretch, where serious - even fatal - accidents occur regularly. To eliminate these hotspots, the trail had to be corrected.
Thus, in spring 2016, the winning consortium FŐMTERV Zrt. - UNITEF 83 Zrt. was awarded the contract for the design of the 2×2 lane 110 km/h highway. The plans have been prepared in such a way that the section between Pápa and Győr can be completed in two phases. The construction works were handed over on 21.09.2020 and, as mentioned above, the handover is currently in progress.
This is how the tasks were distributed
The division of planning tasks within the consortium was then discussed. The trail was divided into 2 parts,
- the section between Pápa - Tét is designed by FŐMTERV Zrt.,
- while the Tét-Győr section was designed by UNITEF’83 Zrt..
As the leader of the consortium, FŐMTERV Zrt. was also responsible for coordinating the design tasks for the entire phase and for developing the appropriate technical content.
This is why the 83 has a new route
Returning to the planning process, Gábor Hevesi explained that the former route and technical condition of the 83 main road did not allow the new 2×2 lane road to be designed with the required capacity. So it was designed and built on a new route, typically parallel to the old main road.
The Paphos airport was important in the planning of the road for several reasons
In particular, he highlighted that a new connecting road to the Pápa base airport has been completed from the junction at the northern end of Pápa: this new section crosses the railway line MÁV at a separate level, so that the access to the airport is no longer obstructed by rail traffic.
Asked what the most interesting part of the work was, the chief engineer again referred to the airport and said that, in addition to the settlements, the location of the existing road network and the topography, they had to take into account a very unusual circumstance: the proximity of the Pápa base airport.
Tracks bypassing the nearby settlement of Takácsi were envisioned on the eastern side of the settlement in the preparatory documents for the FŐMTERV work. However, a problematic situation would have arisen with this trail design:
the route would have been a continuation of the airport runway, so aircraft and vehicles landing and taking off would have interfered with each other, so another solution was chosen. Avoiding Takácsi's interior from the west, the trail was bypassed to avoid the airport runway alignment.
The number of nodes was not set in stone from the start
Gábor Hevesi pointed out that while the route was being drawn, another important issue was to determine the correct location of the nodes. Here, two fundamentally contradictory conditions had to be met:
- there should be as many junctions as possible on the new road 83, in order to allow as much traffic as possible to transfer to the new main road;
- but with each junction, the investment cost increased and the number of potential conflicts on the new route increased, meaning that traffic safety decreased.
The FŐMTERV has found the best ratio in close cooperation with the municipalities concerned.
Communication was key
In this context, the Chief Engineer also highlighted the good communication between the project actors. He said that all stakeholders were involved responsibly in all important decisions. The planned and now constructed route and the associated works were under tight cost control throughout, and all parties involved understood the importance of staying within the financial limits.
Still built a wildlife fence
He then went back to a specific task: he said that although the original preliminary documentation did not include a wildlife fence - although the design speed of 110 km/h would have justified it - the project did not include one. During the design phase, FŐMTERV was warned that there were significant incidences of wildlife crossing the track at several points along the route: in particular, many incidences were reported between Gyarmat and Tét. A wildlife crossing was therefore designed and implemented on this section, and a wildlife protection fence was built.
Bypass road no longer planned
Another challenging task developed in the area of Ménfőcsanak and Gyirmót. As the expert pointed out, in the mid-1990s, the original Highway 83 was given a section bypassing Ménfőcsanak, but over the decades Ménfőcsanak and Gyirmót have been fully built onto the main road.
This created the special situation that the bypass was to have been designed as a bypass: however, no solution was found for its route to allow a speed of 110 km/h. If they had looked for a solution in an easterly direction, they would have run into a contiguous residential area, which would have extended all the way to Highway 82. And to the west, the Rába and its NATURA 2000 nature reserves are natural barriers.
Since no new location for the main road was found, the existing route between Gyirmót and Ménfőcsanak was modified: a so-called temporary section was created, where the speed limit is 70 km/h. The reduced speed made the junctions safer and reduced the noise and vibration impact on the settlements, but still required the construction of noise barriers.
Specific solutions were needed
Another challenge was that the main road had to be designed with a cross-sectional width of 20.5 metres, which is different from the standard for expressways. The position of all elements had to be rethought. For this reason, the structures crossing the main road could not be supported in the dividing lane, so they were constructed with a single superstructure across the entire width.
Research drilling also had to be stopped
Gábor Hevesi also mentioned among the challenges and interesting facts: the new trail approached a hydrocarbon exploration drilling site within the protection distance. No hydrocarbons were eventually found here, only thermal water, so part of the project was to remove it. This is a task that is rarely encountered in the design of a road project," he points out.
And on the section of the new route between Takácsi, Gyarmat and Tét, a network of soil improvement pipes was built before the regime change. The main purpose of this network is to drain stagnant water from agricultural land. Although the system is still operational today, no map of it has survived and it had to be explored. The chief engineer told the newspaper that it was a particular success that only one modification to the reconstruction plan had to be made during the construction phase, after the actual system had been discovered.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November