Road building

Safety and comfort instead of potholes - Road renovation in the Zemplén Hills

Published

Photo: magyarepitok.hu - Tamás Dernovics
The road 3726 between Bózsva and Nyíri in Borsod county is being renovated. The more than four kilometres of the link road are being worked on by HE-DO specialists. During the works, buses and agricultural machinery will continue to be able to travel during the harvest.

As part of a major transport project, the road between Bózsva and Nyíri in Borsod County is being renovated, which will bring significant improvements in both transport between the settlements and traffic safety , according to the HE-DO information sheet. Work began in October 2024 and continued after the winter period, from March 2025. The project, funded by the EU, was commissioned by Magyar Közút Nonprofit Zrt. and is being implemented by HE-DO.

Work is underway to ensure the passage of buses and agricultural machinery

Between Bózsva and Nyíri, between km 0+000 and km 4+333 of road 3726 will be upgraded. The poor condition of the road has caused many problems for road users.

They will be carried out during the project:

  • profile milling of the casing,
  • the replacement of road kerbs,
  • the cleaning of ditches,
  • asphalting,
  • as well as the construction of the landfill.

During the renovation work, special attention will be paid to the uninterrupted movement of agricultural machinery and buses, as the narrow built-up area is a key factor in maintaining traffic flow.

In the first phase of the works, in parallel with the milling of the pavement, the specialists also cleaned the trenches and paved trenches and built the embankment. The next steps will involve the replacement of the raised kerbs, the reconstruction of the culverts under the gateway and the construction of asphalt layers.

They create security

The poor condition of the road caused difficulties for both locals and passing traffic, with potholes not only making travel uncomfortable, but also endangering road safety.
The works are scheduled to be completed in July 2025, after which the renewed road will be fully open to traffic.

Source : Link