It took just 14 months to build the 54.4 metre long double-track railway bridge over the Danube-Tisza canal.
The results of the HUF 800 billion project were presented at a machine launch ceremony: the tracks between the stations to the border of the capital are completed
In addition to the upgrading and electrification of the Soroksár-Kunszentmiklós-Tass-Kelebia railway line, a number of infrastructure improvements related to stations and passenger traffic will be implemented on line 150. Among other things, the Colas...
Colas Út Zrt. is building a new double-track railway bridge over the Danube-Tisza canal on behalf of CTEC Kft..The left track is planned to be completed in early April...
In Dunaharaszti, a railway bridge proving ground developed by STRABAG's bridge construction specialists is being installed to ensure the continuity of construction railway traffic in the Budapest-Belgrade (BuBe) project.
A new underpass with a larger opening will help car and pedestrian traffic in Dunaharaszti.
The public procurement for the design of a separate level crossing of the Kelebia-Baja main road crossing the railway has been published.
In order to accommodate the expected increase in freight traffic, a public tender has been launched for the design of a road bypassing Kiskunlachaza from the north, crossing the railway line on an overpass.
The construction of the bypass will significantly reduce through traffic on the inland section of the settlement.
The ministry submits a comprehensive railway development programme to the government.