In the last period, 20,885 cubic metres of concrete and 4,793 reinforcing steel have been installed in the two buildings by contractors Market Építő Zrt. and Bayer Construct.
At the 40th Hungarian Grand Prix in 2025, Hungaroring will show its new face with the help of Market and Bayer - the first major step in the renovation is being taken by the builders.
The transformation of the complex will continue, with Market and Bayer Construct carrying out major tasks.
The consortium of Market and Bayer Construct wasted no time in getting down to work after the Hungarian Formula 1 Grand Prix.
The first stage of the Hungaroring's refurbishment has been recognised by the International Automobile Federation (FIA) and F1 officials. They asked the professional staff of the Mogyorod track to share their...
To meet deadlines, work was often carried out 24 hours a day, with 400-500 people working on the site at any one time, and a total of 1500 people working on the project.
The Market Építő Zrt. and Bayer Construct specialists are building and dismantling the Hungaroring under renovation at the same time, as sixty days before the Hungarian National...
The biggest of the many challenges is squeezing work between racing seasons in the large-scale development of the Hungaroring, which is progressing on schedule with the Market Építő Zrt....
The Market Építő and Bayer Construct have so far installed 22 kilometres of piles and have also placed 8,000 cubic metres of concrete.
Despite the winter and the wet weather, work is still in full swing on the Hungaroring. The Market Építő Zrt. and Bayer Construct Zrt. construction...