Bound track
The track has been repaired over a stretch of more than 18 kilometres – rail services between Komló and Dombóvár are resuming
Passenger services on the No. 47 Godisa–Komló railway line will resume on 1 August, with trains running between Dombóvár and Komló. The resumption of the service, which has been suspended since August 2023, was preceded by major track maintenance work. According to a statement from the MÁV group, track realignment work was carried out over a total of 18.4 kilometres during the works to ensure operational safety.
Seven level crossings have been rebuilt
The heavy-equipment track maintenance work was carried out by specialists from MÁV. As part of this, 750 tonnes of crushed stone were added to the track; ballast was replenished and track alignment was adjusted; and the track’s correct geometric position and stability were restored using mechanical compaction. The works included the demolition of seven level crossings, followed by their reconstruction once the works were completed. The works affected the areas of Mindszentgodisa, Magyarszék, Mecsekpölöske, Mecsekjánosi and Komló.
A total of 6,500 rail fastening points were repaired
Experts carried out repairs to the holes in the reinforced concrete sleepers and to the rail fixings at 6,500 points. The work also affected the tracks at Komló railway station.
The new passenger information display, which is currently being tested, is to be installed in Mecsekpölöske
Alongside track maintenance, the passenger information infrastructure is also being upgraded. New regional information columns are being installed at stops along Line 47, whilst Komló station will be fitted with a standard wall-mounted passenger information display.
An e-paper terminal is also being installed at the Mecsekpölöske stop. The equipment, which is capable of displaying real-time information, has already been tested at bus stops, but this is the first time it has been used at a railway station.
Passenger trains will run every two hours
From 1 August, passengers will be carried by Bz railcars, which will cover the journey between Dombóvár and Komló in 42 minutes. With the exception of the morning and evening periods, a two-hourly timetable will be introduced, and connections will be provided at Dombóvár to the Mecsek InterCity trains running between Budapest and Pécs, as well as to services bound for Kaposvár and Baja.
With the restoration of the rail link, the 1,490-forint Mecsek day ticket will also become available again. The 24-hour ticket will be valid, amongst other routes, on the Dombóvár–Komló line, on the section of the Budapest–Pécs main line between Dombóvár and Pécs, and on the region’s connecting local bus services.
Source: Link
-
What is being built? 2026. 07. 27.
Construction of Phase VIII of the Somfa Liget residential estate is underway using hybrid construction methods, prefabricated elements and the LEAN organisation model
-
Water management 2026. 07. 27.
Szeged is getting rid of its asbestos-cement and cast-iron pipes
-
What is being built? 2026. 08. 06.
Paks II.: What does the new milestone for Unit 5 mean in the context of the review?
-
Road building 2026. 08. 05.
The main road leading to a key tourist destination in Bihar is being upgraded using cold recycling technology