Road building
Development of several kilometres of road may begin in Rákosmente
The local government of Rákosmente has signed a framework agreement for the execution of road and civil engineering works with the winner of the public procurement with Penta Általános Építőipari Kft.. In the process, they sought a partner for the complex implementation of road renovation works, which, in addition to road construction, pavement construction, paving and car park construction tasks, may also include rainwater drainage or the installation of public lighting.
Rákóczi and Vörösmarty streets in Rákoshegy may be renovated
The first part of the two-part public procurement project involves the reconstruction of the entire length of Rákóczi Street in District XVII (between Lőrinci Road and the boundary of the residential area), as well as the reconstruction of Vörösmarty Street between Ferihegyi Road and Lőrinci Road. The work must be carried out together with the construction of a one-sided pavement, the associated drainage, the expansion of the public lighting network, the design of traffic technology, and, if necessary, tree felling and replacement.
Main quantities:
- road construction: 2188 fm
- „K” border: 1865 fm
- recessed edging: 3464 fm
- highlighted border: 30 fm
- garden edging: 2965 running metres
- pavement construction: 3150 m2
- Construction of motor vehicle gateways: 2295 m2
- Construction of asphalt-paved road: 9,597 m2
- Construction of covered trench from riverbed elements: 986 running metres
- Sewer construction using DN 315 PVC-U pipes: 22 running metres
- Sewer construction using DN 400 PVC-U pipes: 434 running metres
- construction of drains with covers: 47 units
- speed reduction threshold: 14 pcs
In Rákoskeresztúr, Egervár Street may also undergo transformation, alongside Ágas Street, Bölcske Street and Börzönce Street.
The second phase of the project involves the complete renovation of Ágas Street (between Pesti Road and Cséplő Street), Bölcske Street (between Börzönce Street and Egerszeg Street), Börzönce Street (between Balassagyarmat Street and Egervár Street), and the entire length of Egervár Street (between Börzönce Street and Egerszeg Street) will be renovated by the winning bidder Penta, including the construction of a one-sided pavement, the associated drainage system, the expansion of the public lighting network, traffic engineering, and, if necessary, tree felling and replacement.
Main quantities:
- road construction: 932 linear metres
- „K” border: 852 fm
- recessed edging: 1295 running metres
- garden edging: 837 running metres
- pavement construction: 1002 m2
- construction of motor vehicle gateways: 843 m2
- Construction of asphalt road surface: 3861 m2
- Sewer construction using DN 315 PVC-U pipes: 721 running metres
- Sewer construction using DN 400 PVC-U pipes: 61 running metres
- construction of drains with covers: 33 units
- speed reduction threshold: 3 pcs
Source: Link
-
Current at 2026. 09. 09.
A first-hand look at a career in engineering – Duna Group Szabadegyetem is back
-
Climate-X 2026. 09. 09.
Nyíregyháza Spartacus FC goes green – four hundred solar panels to be installed on the stadium roof
-
Bound track 2026. 09. 15.
Nearly 50,000 people travel on it every day – the refurbishment of the Cegléd main line continues
-
Current at 2026. 09. 09.
Rental flats, Rákosrendező, decentralisation – important ideas were put forward on the Real Estate Beach Conference stage