What is being built?
Construction of Phase VIII of the Somfa Liget residential estate is underway using hybrid construction methods, prefabricated elements and the LEAN organisation model
Located near Népliget, Somfa Liget residential estate has been the subject of several reports in our newspaper, including the seventh phase of the project: the residential building at Xth District, which, thanks to its meticulous design and high-quality construction, was awarded the 2024 Construction Industry Quality Award in the multi-unit residential building category.
The apartment block, which is currently under construction as part of the latest, Phase VIII, meets today’s architectural and interior design standards and complies with the very latest thermal insulation standards.
In the case of the current residential building, three building blocks are being constructed on a shared basement level measuring 3,103 m2. The two outer wings will comprise a basement, ground floor and six storeys, whilst the central wing will comprise a basement, ground floor and seven storeys, in which a total of 137 flats will be created. The total net floor area of the building is 11,332 m2.
The project is being carried out as part of the I-S Ceglédi 2025 Consortium by INETON Kft. and the STRABAG-MML Kft. is being implemented by the investor OTP Ingatlan Zrt.. The project manager for the consortium leader, INETON Kft., is Martin Dán, and for STRABAG-MML Kft., it is Csaba Knoll.
The construction site was handed over on 27 February 2026; the structural work is due to be completed by March 2027, the buildings are due to be sealed by May 2027, whilst the technical handover is due to begin in autumn 2027.
The foundations have been completed and structural work has begun
At present, the foundations have been fully completed, whilst structural work is 5 per cent complete.
The block of flats is built on an 80-centimetre-thick, watertight reinforced concrete foundation slab. The excavation pit was formed using sloping earthworks – with sheet piling used in places to define the work area – whilst a vacuum well dewatering system is being used due to the high water table.
„A flat foundation has been laid using an 80-centimetre-thick foundation slab. To prepare the foundation, we excavated the site using a sloping cut, and we are operating a vacuum well dewatering system to lower the groundwater level by 3 metres, which we must maintain until the slab above the first floor is completed” – said József Cserháti, the site manager responsible for structural works.
During the construction of the building, a number of prefabricated elements manufactured by INETON Kft. are used, including shell-panel floor slabs, prefabricated stair stringers, balcony parapets, roof parapets and space-defining façade wall panels, which enable faster construction.
However, according to the expert, customer-requested changes require a great deal of coordination, as the prefabricated components are manufactured well in advance of installation.
Hybrid heating system and renewable energy
The building’s energy supply is provided by a hybrid system comprising an air-to-water heat pump and four condensing boilers (110 kW each).
Ákos Tiszóczi, mechanical engineer and facilities manager, explained that during the transitional period, the heat pump will supply the building, whilst in the event of low outdoor temperatures (below +5°C), the condensing boilers will also be switched on gradually.
The system automatically switches between the two heat sources based on the outside temperature, ensuring that at least 25 per cent of the building’s energy consumption comes from renewable energy sources.
Radiator heating systems /strong> are being installed in the buildings, fitted with individual heat meters. The heat emitters are sheet steel panel radiators and bathroom towel-drying radiators; heating in the flats is controlled by a wall-mounted thermostat in the living room and by thermostatic valve heads on the radiators. Domestic hot water is produced and stored by a centralised system, from which it is distributed to all flats in the building. Each flat is pre-fitted for the subsequent installation of split-system air-conditioning units.
State-of-the-art electrical and safety systems
The block of flats is supplied with 3×1,250-ampere power; safety in the communal areas is ensured by emergency lighting, a fire alarm system, heat and smoke extraction, a CO detection system and a pressurised stairwell.
„The shared mechanical systems are controlled by an automation system” – explained István Brezovszky, the electrical facilities manager.
Aluminium cladding is also being introduced as a new façade element
The design of the façade essentially follows the technical solutions used in previous phases, featuring 10-centimetre-thick EPS thermal insulation, a plastered façade and plastic windows and doors.
Eszter Smekálné Oláh, a design engineer, explains that, as a new feature, Prefa aluminium cladding will also be used as a decorative element on certain façade surfaces.
The disciplines are being aligned in line with the LEAN approach
When constructing a residential building of this size, the structural, mechanical, electrical, façade and interior finishing teams all work simultaneously; this is why ongoing coordination is of paramount importance.
A key role in this is played by the LEAN system used by STRABAG, which is based on the continuous optimisation of processes, the reduction of losses and the coordination of workflows. The essence of the method is that all participants jointly plan the tasks for the coming period on a weekly basis, enabling the various departments to build on each other’s work and proceed without any conflicts.
„We hold weekly internal coordination meetings – amongst the main contractors – where we exchange information, clarify details and work together to mitigate risks in line with the LEAN approach; we then communicate the final outcome using all available means – the construction log, subcontractor coordination, joint weekly scheduling in accordance with LEAN, and the BIM platform – to the subcontractors,” emphasised Zsolt Bencze, Head of General Contracting.
Construction traffic is organised in a way that takes the local environment into account
Traffic is being channelled via Ceglédi út to minimise disruption to the surrounding residential areas. In consultation with the local council, the contractors are carrying out work that generates significant noise only on weekdays.
Zoltán Tímár, the site manager, explained that quiet operation was a key consideration for the continuously running dewatering pumps, whilst the access routes were regularly hosed down during the earthworks to reduce dust.
Particular attention must be paid to the construction of the underground car park and the organisation of the worksite
Due to the high water table, the cellar walls are constructed using a watertight reinforced concrete structure, which requires particular attention to the concreting process, the construction schedule and the finishing work. In addition, certain rooms with dust-dry requirements will also be fitted with additional external waterproofing.
„As the reference groundwater level is 2.65 metres above the top surface of the floor slab, we must construct a watertight reinforced concrete cellar wall, whilst ensuring that the correct concrete technology, phased construction and finishing are applied. Furthermore, we have rooms with dust-dry requirements, where we even need to install additional external waterproofing” – said Péter Jenei, a preparatory engineer.
Construction is further complicated by the fact that, from the laying of the foundations until the completion of the floor slab above the first floor, the site is considered to be almost entirely a built-up work area; consequently, access is only possible on foot via the building itself. To mitigate this, the contractors are also incorporating the neighbouring plots into their organisation. This is where the material storage areas have been set up, from which tower cranes transport the necessary components to the construction site.
When organising the workspace, the principles of the STRABAG’s own 5S system are also applied; this is a methodology designed to ensure an orderly and safe working environment. The English acronym encompasses five basic principles: Sort (sorting), Systematise (organising), Shine (keeping clean), Standardise (standardisation) and Self-discipline (self-discipline). This is complemented by the company’s „Stop! – Think! – Act!” approach to health and safety, which prioritises safe working practices.
According to the contractors, the biggest challenge of the project is not a technical detail, but the extremely tight deadline.
The construction of Phase VIII will require a total of approximately 7,662 cubic metres of concrete, 851 tonnes of reinforcing steel and 12,342 square metres of masonry materials.
STRABAG TEAM OF EXPERTS:
- József Cserháti – site manager responsible for structural works
- István Brezovszky – electrical installations manager
- Ákos Tiszóczi – mechanical engineer in charge of the facility
- Eszter Smekálné Oláh – design engineer
- Zsolt Bencze – Head of General Contracting
- Zoltán Tímár – site manager
- Péter Jenei – design engineer
- Martin Dán – Project Manager (INETON)
- Csaba Knoll – project manager
Source: Link
-
Water management 2026. 07. 27.
Szeged is getting rid of its asbestos-cement and cast-iron pipes
-
What is being built? 2026. 08. 06.
Paks II.: What does the new milestone for Unit 5 mean in the context of the review?
-
Road building 2026. 08. 05.
The main road leading to a key tourist destination in Bihar is being upgraded using cold recycling technology
-
Climate-X 2026. 08. 05.
STRABAG is relieving the strain on the electricity system through plant shutdowns and reorganised production