What is being built?
Contemporary structures for neo-baroque headquarters
Recently, reported that the central bank's neo-baroque headquarters had been restored through a large-scale development project. As we were able to see for ourselves during a tour of the building, one of Ignác Alpár's most famous buildings has been reborn as a modern, energy-efficient office building, with the representative spaces having been precisely reconstructed.
The headquarters on Szabadság Square was designed by TIBA Építész Stúdió and was renovated by Raw Development Kft.. while the reinforced concrete structural work involved in the conversion and extension project was carried out by Épszerk-Pannónia Invest Kft.. In this article, we take a closer look at the tasks and difficulties involved in structural engineering, and learn about the unique challenges of adding modern technology to a historic building.
A complete reconstruction of the MNB building was carried out, during which the previous covering of the courtyard above ground level was removed and the courtyard of the building was given a 1320 m2 glass dome, creating a large, bright interior atrium. Not only was the motif system of the building preserved during the renovation, but the balustrades with the monumental vine-floral ornamentation, the monumental chandeliers and the leaded glass panels were also reconstructed.
New structures, remaining values
As we learned from the staff at ÉPI, new structures also had to be built in the original building: pillars (freestanding and embedded in existing brick walls), walls, beams, frames, slabs, lift shafts, mechanical shafts and stairs were installed between the historic walls. The tasks of ÉPI were coordinated by two professionals who had previously received the Engineer of the Month award: while Bálint Szász, as director of the structural engineering division, was responsible for the structural superstructure of the additional floors (and en bloc) with his team, Péter Ilkei, chief engineer of the facility, and his team oversaw the structural conversion of the existing parts of the building. According to their information
Two storeys of roof construction were added to the former slab-on-grade, which meant that ÉPI had to build pillars, walls, beams, slabs, sloping slab-on-grade and stairs on the new parts of the building.
A number of additional structures, necessary upgrades and replacements were needed to bring the building up to the quality of its former quality in terms of spatial experience, while at the same time bringing its structure up to contemporary standards. An important part of this was the installation of steel opening replacement beams, which had to be fitted into the existing brickwork to accommodate the large number of new openings.
The nesting and mass splitting of brickwork required special attention from the structural engineers, within which the
- nesting (the new slab is fixed into the nests previously cut into the brick walls), the
- beam cutting (the positions of the beams for the new steel beams had to be cut out in the brickwork beforehand), and
- the most challenging task was the mass demolition of the brick walls (with the construction of preliminary supports and subsequent opening replacement structures).
Both parts of the building, including the listed and the new floors, underwent major reinforced concrete construction: the main works included the reinforcement of the pillars, the installation of the opening beams, the creation of the frames for the new openings, the installation of new slabs, 12 lift shafts, four mechanical shafts and four electrical shafts, as well as the installation of stairs.
"Another exciting challenge," they pointed out, "was the construction of the high pitched sloping slopes with variable roof heights, which gives the roof a spectacular architectural appearance."
Prefabrication is also beneficial in a listed environment
Several new reinforced concrete structures required special attention because of the listed heritage sites in their vicinity. To create the large new openings, the contractors used heavy-duty scaffolding (Doka SL-1) to build the preliminary spans, the design and negotiation of which, as they informed me, was an extremely complex and lengthy process.
During the complete replacement of the floor slab above the third floor of the new building section, new prefabricated ribbed prestressed shell panels and reinforced concrete floor structures were installed in place of the building's former top floor.
Both the over-framed, filigree, prestressed bark panel slab elements and the reinforced concrete are connected to the existing building by nesting joints. And the precision of the prefabricated elements helped the contractors to work to millimetre-precise dimensions to link to the listed masonry.
Serious difficulties in organisation
"Probably one of the biggest challenges," they said, "was getting the concrete in and out of the building, which we did with an installed concrete pump, piping up to 100 metres."
The installation of the two 1.5-tonne steel beams also proved to be a complex task. After being brought into the building, they had to be raised to a height of about six metres and positioned in a cavity in the brickwork; they were then wedged to the brick structure by means of a circular concrete pour. A further difficulty was that there was little space for storage around the building, so much of the material had to be stored on the roof.
Looking back on their experience of the construction, the ÉPI colleagues added that although they had accurately assessed the structure of the building beforehand, there were still surprises during the construction, which required a daily SOS response.
"Compared to a new building, there was a lot more design consultation, we were in daily contact with the structural engineer; and we must say that the relationship between the stakeholders was very good. All parties involved (the structural engineer, the general contractor and the investor) were constructive in their approach to the problems that arose, and everyone was keen to find the best solution as quickly as possible."
Source : Link
-
Industry news 2026. 08. 18.
Students were introduced to the high-tech construction industry at BME’s field camp in Göd
-
Bound track 2026. 08. 17.
New pedestrian crossings and a junction with traffic lights are being built in Angyalföld
-
What is being built? 2026. 08. 18.
Hungary’s new McDonald’s restaurant has moved into a modernist listed building in the centre of Budapest
-
What is being built? 2026. 08. 18.
New paving, a playground and visitor facilities are being planned for the Várkör area in Pannonhalma